Executive
Summary
The Hong Kong-Zhuhai-Macao
Bridge (HZMB) Hong Kong Link Road (HKLR) serves to connect the HZMB Main Bridge
at the Hong Kong Special Administrative Region (HKSAR) Boundary and the HZMB
Hong Kong Boundary Crossing Facilities (HKBCF) located at the north eastern
waters of the Hong Kong International Airport (HKIA).
The HKLR project has been
separated into two contracts. They are Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section between Scenic Hill and
Hong Kong Boundary Crossing Facilities (hereafter referred to as the Contract)
and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link
Road-Section between HKSAR Boundary and Scenic Hill.
China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department as the
Contractor to undertake the construction works of Contract No. HY/2011/03. The main works of the Contract include
land tunnel at Scenic Hill, tunnel underneath Airport Road and Airport Express
Line, reclamation and tunnel to the east coast of the Airport Island, at-grade
road connecting to the HKBCF and highway works of the HKBCF within the Airport
Island and in the vicinity of the HKLR reclamation. The Contract is part of the HKLR Project
and HKBCF Project, these projects are considered to be ˇ§Designated Projectsˇ¨,
under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap
499) and Environmental Impact Assessment (EIA) Reports (Register No.
AEIAR-144/2009 and AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on 22 December
2014 and 11 April 2016, respectively. These documents are available through the
EIA Ordinance Register. The construction phase of Contract was commenced on 17 October 2012.
BMT Asia Pacific Limited
has been appointed by the Contractor to implement the Environmental Monitoring
& Audit (EM&A) programme for the Contract in accordance with the
Updated EM&A Manual for HKLR (Version 1.0) and will be providing
environmental team services to the Contract.
This is the sixty-sixth Monthly EM&A report for the Contract which summarizes the monitoring
results and audit findings of the EM&A programme during the reporting
period from 1 to 31 March 2018.
Environmental
Monitoring and Audit Progress
The monthly EM&A
programme was undertaken in accordance with the Updated EM&A Manual for
HKLR (Version 1.0). A summary of
the monitoring activities during this reporting month is listed below:
1-hr TSP Monitoring
|
2,
8, 14, 20, 26 and 29 March 2018
|
24-hr TSP Monitoring
|
1,
7, 13, 19, 23 and 28 March 2018
|
Noise Monitoring
|
8,
14, 20, and 26 March 2018
|
Water Quality Monitoring
|
2,
5, 7, 9, 12, 14, 16, 19, 21, 23, 26, 28 and 30 March 2018
|
Chinese White Dolphin
Monitoring
|
8,
12, 20 and 23 March 2018
|
Mudflat Monitoring (Sedimentation Rate)
|
18
March 2017
|
Mudflat Monitoring (Ecology)
|
3,
4, 11, 14, 17 and 21 March 2018
|
Site Inspection
|
1,7,
14, 21 and 27 March 2018
|
Due to foggy weather and
low visibility, water quality monitoring at all stations during flood tide on 5
March 2018 were cancelled.
Due to the boat
unavailability, the dolphin monitoring was rescheduled from 6 March 2018
to 8 March 2018 and from 16 March 2018 to 20 March 2018.
Breaches of Action and Limit Levels
A summary of environmental
exceedances for this reporting month is as follows:
Environmental Monitoring
|
Parameters
|
Action Level (AL)
|
Limit Level (LL)
|
Air Quality
|
1-hr TSP
|
0
|
0
|
24-hr TSP
|
0
|
0
|
Noise
|
Leq (30 min)
|
0
|
0
|
Water Quality
|
Suspended solids level (SS)
|
2
|
0
|
Turbidity level
|
0
|
0
|
Dissolved oxygen level (DO)
|
0
|
0
|
Complaint Log
There was one complaint received
in relation to the environmental impacts (Cleanliness problem at East Coast
Road) which was mentioned in Monthly EM&A Report for December 2017.
Complaint investigation was undertaken. Based on the investigation
result, there is no direct evidence showing that that the complaint is related
to Contract No. HY/2011/03.
A summary of environmental
complaint for previous reporting month (December 2017) is as follows:
Environmental Complaint No.
|
Date of Complaint Received
|
Description of Environmental Complaint
|
COM-2017-129
|
ENPOˇ¦s email to the Supervising Officerˇ¦s
Representative and Contractor on 8 January 2018 that HyD received a
complaint lodged by a member of the public regarding cleanliness problem at
East Coast Road on 29 December 2017
|
Cleanliness problem at East Coast Road
|
There was one complaint
received in relation to the environmental impacts for Monthly EM&A Report
for February 2018. A follow-ups of complaint No. COM-2018-132 was received during reporting period. Complaint Investigation is being
undertaken.
A summary of environmental
complaint for previous reporting month (February 2018) and during reporting
month is as follows:
Environmental Complaint No.
|
Date of Complaint Received
|
Description of Environmental Complaint
|
COM-2018-132
|
HyD (SOR referred the
email from HyD to Contractor and ET on 13 February 2018) and EPD (ENPO
referred the email from EPD to SOR, SOR sent the email to Contractor and ET
on 14 February 2018)
|
Complaint about Dust, Water Quality, Construction Waste, Noise and Vibration
for the Contract
|
Follow-ups of Complaint
No COM-2018-132
|
HyD (SOR referred the email from HyD to the Contractor and ET on 16
March) and EPD (ENPO referred the email from EPD to SOR, who sent the email
to the Contractor and ET on 21 March 2018)
|
Dust and Construction Waste
|
Notifications
of Summons and Prosecutions
There were no
notifications of summons or prosecutions received during this reporting month.
Reporting
Changes
This report has been
developed in compliance with the reporting requirements for the subsequent
EM&A reports as required by the Updated EM&A Manual for HKLR (Version
1.0).
The proposal for the change
of Action Level and Limit Level for suspended solid and turbidity was approved
by EPD on 25 March 2013.
The revised Event and
Action Plan for dolphin monitoring was approved by EPD on 6 May
2013.
The original monitoring
station at IS(Mf)9 (Coordinate: 813273E, 818850N) was observed inside the
perimeter silt curtain of Contract HY/2010/02 on 1 July 2013, as such the
original impact water quality monitoring location at IS(Mf)9 was temporarily
shifted outside the silt curtain. As advised
by the Contractor of HY/2010/02 in August 2013, the perimeter silt curtain was
shifted to facilitate safe anchorage zone of construction barges/vessels until
end of 2013 subject to construction progress. Therefore, water quality monitoring
station IS(Mf)9 was shifted to 813226E and 818708N since 1 July 2013. According to the water quality
monitoring teamˇ¦s observation on 24 March 2014, the original monitoring
location of IS(Mf)9 was no longer enclosed by the perimeter silt curtain of
Contract HY/2010/02. Thus, the impact water quality monitoring works at the
original monitoring location of IS(Mf)9 has been resumed since 24 March 2014.
Transect lines 1, 2, 7, 8,
9 and 11 for dolphin monitoring have been revised due to the obstruction of the
permanent structures associated with the construction works of HKLR and the
southern viaduct of TM-CLKL, as well as provision of adequate buffer distance
from the Airport Restricted Areas.
The EPD issued a memo and confirmed that they had no objection on the
revised transect lines on 19 August 2015.
The water quality
monitoring stations at IS10 (Coordinate: 812577E, 820670N) and SR5 (811489E,
820455N) are located inside Hong Kong International Airport (HKIA) Approach
Restricted Areas. The previously granted Vessel's Entry Permit for accessing
stations IS10 and SR5 were expired on 31 December 2016. During the permit
renewing process, the water quality monitoring location was shifted to IS10(N)
(Coordinate: 813060E, 820540N) and SR5(N) (Coordinate: 811430E, 820978N) on 2,
4 and 6 January 2017 temporarily. The permit has been granted by Marine
Department on 6 January 2017. Thus, the impact water quality monitoring works
at original monitoring location of IS10 and SR5 has been resumed since 9
January 2017.
Transect lines 2, 3, 4, 5,
6 and 7 for dolphin monitoring have been revised and transect line 24 has been
added due to the presence of a work zone to the north of the airport platform
with intense construction activities in association with the construction of
the third runway expansion for the Hong Kong International Airport. The EPD
issued a memo and confirmed that they had no objection on the revised transect
lines on 28 July 2017. The alternative dolphin transect lines are adopted
starting from Augustˇ¦s dolphin monitoring.
A new water quality monitoring team has been employed for carrying out
water quality monitoring work for the Contract starting from 23 August 2017. Due to marine work of the Expansion of Hong Kong
International Airport into a Three-Runway System (3RS Project), original
locations of water quality monitoring stations CS2, SR5 and IS10 are enclosed
by works boundary of 3RS Project. Alternative impact water quality monitoring
stations, naming as CS2(A), SR5(N) and IS10(N) was approved on 28 July 2017 and
were adopted starting from 23 August 2017 to replace the original locations of
water quality monitoring for the Contract.
The role and responsibilities as the ET Leader of the Contract was temporarily
taken up by Mr Willie Wong instead of Ms Claudine Lee from 25 September 2017 to
31 December 2017.
Water quality monitoring
station SR10A(N) (Coordinate: 823644E, 823484N) was unreachable on 4 October
2017 during flood tide as fishing activities were observed. As such, the water
monitoring at station SR10A(N) was conducted at Coordinate: 823484E, 823593N
during flood tide on 4 October 2017 temporarily.
The topographical condition of the water monitoring
stations SR3 (Coordinate: 810525E, 816456N), SR4 (Coordinate: 814760E, 817867N),
SR10A (Coordinate: 823741E, 823495N) and SR10B (Coordinate: 823686E, 823213N) cannot
be accessed safely for undertaking water quality monitoring. The water quality
monitoring has been temporarily conducted at alternative stations, namely
SR3(N) (Coordinate 810689E, 816591N), SR4(N) (Coordinate: 814705E, 817859N) and
SR10A(N) (Coordinate: 823644E, 823484N) since 1 September 2017. The water
quality monitoring at station SR10B was temporarily conducted at Coordinate:
823683E, 823187N on 1, 4, 6, 8 September 2017 and has been temporarily
fine-tuned to alternative station SR10B(N2) (Coordinate: 823689E, 823159N)
since 11 September 2017. Proposal for permanently relocating the aforementioned
stations was approved by EPD on 8 January 2018.
The future key issues include
potential noise, air quality, water quality and ecological impacts and waste
management arising from the following construction activities to be undertaken
in the upcoming month:
- Dismantling/trimming
of Temporary 40mm Stone Platform for Construction of Seawall at Portion X;
- Construction of
Seawall at Portion X;
- Loading and Unloading
Filling Materials at Portion X;
- Backfilling at Scenic
Hill Tunnel (Cut & Cover Tunnel) at Portion X;
ˇP
Works for Diversion of
Airport Road;
- Utilities Detection at
Airport Road / Airport Express Line/ East Coast Road;
- Establishment of Site
Access at Airport Road / Airport Express Line/ East Coast Road;
- E&M/ Backfilling/
Bitumen works for HKBCF to Airport Tunnel West (Cut & Cover Tunnel) at
Airport Road;
- E&M/ Backfilling/ Bitumen
works for HKBCF to Airport Tunnel East (Cut & Cover Tunnel) at Portion
X;
ˇP
Finishing Works for
Highway Operation and Maintenance Area Building at Portion X; and
ˇP
Finishing Works for
Scenic Hill Tunnel West Portal Ventilation building at West Portal.
1.1.2 The HKLR project has been
separated into two contracts. They
are Contract
No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road-Section
between Scenic Hill and Hong Kong Boundary Crossing Facilities (hereafter
referred to as the Contract) and Contract No. HY/2011/09 Hong Kong-Zhuhai-Macao
Bridge Hong Kong Link Road-Section between HKSAR Boundary and Scenic Hill.
1.1.3 China State Construction
Engineering (Hong Kong) Ltd. was awarded by Highways Department (HyD) as the Contractor to undertake
the construction works of Contract No. HY/2011/03. The Contract is part of the HKLR Project
and HKBCF Project, these projects are considered to be ˇ§Designated Projectsˇ¨,
under Schedule 2 of the Environmental Impact Assessment (EIA) Ordinance (Cap
499) and Environmental Impact Assessment (EIA) Reports (Register No.
AEIAR-144/2009 and AEIAR-145/2009) were prepared for the Project. The current Environmental Permit (EP)
EP-352/2009/D for HKLR and EP-353/2009/K for HKBCF were issued on 22 December
2014 and 11 April 2016, respectively. These documents are available through the
EIA Ordinance Register. The construction
phase of Contract was commenced on 17
October 2012. The works area WA7 was handed over to other party on 31 January
2018. Figure 1.1 shows the project site boundary. The works areas are shown in Appendix O.
1.1.4 The Contract includes the following key aspects:
ˇP
New reclamation along
the east coast of the approximately 23 hectares.
ˇP
Tunnel of Scenic Hill
(Tunnel SHT) from Scenic Hill to the new reclamation, of approximately 1km in
length with three (3) lanes for the east bound carriageway heading to the HKBCF
and four (4) lanes for the westbound carriageway heading to the HZMB Main
Bridge.
ˇP
An abutment of the
viaduct portion of the HKLR at the west portal of Tunnel SHT and associated
road works at the west portal of Tunnel SHT.
ˇP
An at grade road on
the new reclamation along the east coast of the HKIA to connect with the HKBCF,
of approximately 1.6 km along dual 3-lane carriageway with hard shoulder for
each bound.
ˇP
Road links between
the HKBCF and the HKIA including new roads and the modification of existing
roads at the HKIA, involving viaducts, at grade roads and a Tunnel HAT.
ˇP
A highway operation
and maintenance area (HMA) located on the new reclamation, south of the
Dragonair Headquarters Building, including the construction of buildings,
connection roads and other associated facilities.
ˇP
Associated civil,
structural, building, geotechnical, marine, environmental protection,
landscaping, drainage and sewerage, tunnel and highway electrical and
mechanical works, together with the installation of street lightings, traffic
aids and sign gantries, water mains and fire hydrants, provision of facilities
for installation of traffic control and surveillance system (TCSS),
reprovisioning works of affected existing facilities, implementation of
transplanting, compensatory planting and protection of existing trees, and
implementation of an environmental monitoring and audit (EM&A) program.
1.1.6 BMT Asia Pacific Limited has been
appointed by the Contractor to implement the EM&A programme for the
Contract in accordance with the Updated EM&A Manual for HKLR (Version 1.0) for
HKLR and will be providing environmental team services to the Contract. Ramboll
Hong
Kong Limited was employed by HyD as the Independent
Environmental Checker (IEC) and Environmental Project Office (ENPO) for the
Project. The project organization with regard to the
environmental works is as follows.
1.2.1
The project
organization structure and lines of communication with respect to the on-site
environmental management structure is shown in Appendix A. The key personnel contact names and
numbers are summarized in Table 1.1.
Table 1.1 Contact
Information of Key Personnel
Party
|
Position
|
Name
|
Telephone
|
Fax
|
Supervising
Officerˇ¦s Representative
(Ove Arup & Partners Hong Kong Limited)
|
(Chief Resident Engineer, CRE)
|
Robert Antony Evans
|
3968 0801
|
2109 1882
|
Environmental Project Office / Independent Environmental Checker
(Ramboll Hong Kong Limited)
|
Environmental Project Office Leader
|
Y. H. Hui
|
3465 2888
|
3465 2899
|
Independent Environmental Checker
|
Antony Wong
|
3465 2888
|
3465 2899
|
Contractor
(China State Construction Engineering (Hong Kong) Ltd)
|
Project Manager
|
S. Y. Tse
|
3968 7002
|
2109 2588
|
Environmental Officer
|
Federick Wong
|
3968 7117
|
2109 2588
|
Environmental Team
(BMT Asia Pacific)
|
Environmental Team Leader
|
Claudine Lee
|
2241 9847
|
2815 3377
|
Environmental Team
(BMT Asia Pacific)
|
Deputy Environmental Team Leader
|
Willie Wong
|
2241 9821
|
2815 3377
|
24 hours complaint
hotline
|
---
|
---
|
5699 5730
|
---
|
|
1.3
Construction Programme
1.3.1
A copy of the
Contractorˇ¦s construction programme is provided in Appendix B.
1.4
Construction Works Undertaken During the
Reporting Month
1.4.1 A summary of the construction activities undertaken
during this reporting month is shown in
Table 1.2.
Table 1.2 Construction
Activities During Reporting Month
Description of Activities
|
Site Area
|
Dismantling/trimming
of temporary 40mm stone platform for construction of seawall
|
Portion X
|
Construction
of seawall
|
Portion X
|
Loading
and unloading of filling materials
|
Portion X
|
Backfilling
at Scenic Hill Tunnel (Cut & Cover Tunnel)
|
Portion X
|
Works for diversion
|
Airport Road
|
Utilities detection
|
Airport Road/ Airport
Express Line/ East Coast Road
|
Establishment of site access
|
Airport Road/ Airport
Express Line/ East Coast Road
|
E&M/ Backfilling/ Bitumen works for HKBCF
to Airport Tunnel West (Cut & Cover Tunnel)
|
Airport Road
|
E&M/ Backfilling/ Bitumen works for HKBCF
to Airport Tunnel East (Cut & Cover Tunnel)
|
Portion X
|
Finishing
works for Highway Operation and Maintenance Area Building
|
Portion X
|
Finishing
works for Scenic Hill Tunnel West Portal Ventilation building
|
West Portal
|
2.1
Monitoring
Requirements
2.1.1 In accordance with
the Contract Specific EM&A Manual, baseline 1-hour and 24-hour TSP levels
at two air quality monitoring stations were established. Impact 1-hour TSP monitoring was
conducted for at least three times every 6 days, while impact 24-hour TSP
monitoring was carried out for at least once every 6 days. The Action and Limit Level for 1-hr TSP
and 24-hr TSP are provided in Table 2.1 and
Table 2.2, respectively.
Table 2.1 Action
and Limit Levels for 1-hour TSP
Monitoring Station
|
Action Level, µg/m3
|
Limit Level, µg/m3
|
AMS 5 ˇV Ma Wan Chung Village (Tung Chung)
|
352
|
500
|
AMS 6 ˇV Dragonair / CNAC (Group) Building (HKIA)
|
360
|
Table 2.2 Action and
Limit Levels for 24-hour TSP
Monitoring Station
|
Action Level, µg/m3
|
Limit Level, µg/m3
|
AMS 5 ˇV Ma Wan Chung Village (Tung Chung)
|
164
|
260
|
AMS 6 ˇV Dragonair / CNAC (Group) Building (HKIA)
|
173
|
260
|
2.2.1 24-hour TSP air
quality monitoring was performed using High Volume Sampler (HVS) located at
each designated monitoring station. The HVS meets all the requirements of the Contract
Specific EM&A Manual. Portable
direct reading dust meters were used to carry out the 1-hour TSP
monitoring. Brand and model of the
equipment is given in Table 2.3.
Table 2.3 Air
Quality Monitoring Equipment
Equipment
|
Brand and Model
|
Portable direct reading dust meter (1-hour
TSP)
|
Sibata Digital Dust Monitor (Model No.
LD-3B)
|
High Volume Sampler
(24-hour TSP)
|
Tisch Environmental Mass Flow Controlled
Total Suspended Particulate (TSP) High Volume Air Sampler (Model No. TE-5170)
|
2.3.1 Monitoring locations
AMS5 and AMS6 were set up at the proposed locations in accordance
with Contract Specific EM&A Manual.
2.3.2
Figure 2.1 shows the locations
of monitoring stations. Table 2.4
describes the details of the monitoring stations.
Table 2.4 Locations
of Impact Air Quality Monitoring Stations
Monitoring
Station
|
Location
|
AMS5
|
Ma Wan Chung Village (Tung Chung)
|
AMS6
|
Dragonair / CNAC (Group) Building (HKIA)
|
2.4.1 Table 2.5
summarizes the monitoring parameters, frequency and duration of impact TSP
monitoring.
Table 2.5 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter
|
Frequency
and Duration
|
1-hour TSP
|
Three times every 6 days while the highest dust impact was expected
|
24-hour TSP
|
Once every 6 days
|
2.5.1
24-hour TSP Monitoring
(a) The HVS was installed in the vicinity of the air sensitive receivers.
The following criteria were considered in the installation of the HVS.
(i) A horizontal platform with appropriate support to secure the sampler
against gusty wind was provided.
(ii) The distance between the HVS and any obstacles, such as buildings, was
at least twice the height that the obstacle protrudes above the HVS.
(iii) A minimum of 2 meters separation from walls, parapets and penthouse for
rooftop sampler was provided.
(iv) No furnace or incinerator flues are nearby.
(v) Airflow around the sampler was unrestricted.
(vi) Permission was obtained to set up the samplers and access to the monitoring
stations.
(vii) A secured supply of electricity was obtained to operate the samplers.
(viii) The sampler was located more than 20 meters from any dripline.
(ix) Any wire fence and gate, required to protect the sampler, did not
obstruct the monitoring process.
(x) Flow control accuracy was kept within ˇÓ2.5% deviation over 24-hour
sampling period.
(b)
Preparation of Filter Papers
(i)
Glass fibre filters, G810 were labelled and sufficient filters that were
clean and without pinholes were selected.
(ii)
All filters were equilibrated in the conditioning environment for 24
hours before weighing. The conditioning environment temperature was around 25 ˘XC and not variable by more than ˇÓ3 ˘XC; the relative humidity (RH) was
< 50% and not variable by more than ˇÓ5%. A convenient working RH was 40%.
(iii)
All filter papers were prepared and analysed by ALS Technichem (HK) Pty
Ltd., which is a HOKLAS accredited laboratory and has comprehensive quality
assurance and quality control programmes.
(c)
Field Monitoring
(i) The power supply was checked to ensure the HVS works properly.
(ii) The filter holder and the area surrounding the filter were cleaned.
(iii) The filter holder was removed by loosening the four bolts and a new
filter, with stamped number upward, on a supporting screen was aligned
carefully.
(iv) The filter was properly aligned on the screen so that the gasket formed
an airtight seal on the outer edges of the filter.
(v)
The swing bolts were fastened to hold the filter holder down to the frame. The pressure applied was sufficient to
avoid air leakage at the edges.
(vi) Then the shelter lid was closed and was secured with the aluminium
strip.
(vii) The HVS was warmed-up for about 5 minutes to establish run-temperature
conditions.
(viii) A new flow rate record sheet was set into the flow recorder.
(ix)
On site temperature and atmospheric pressure readings were taken and the
flow rate of the HVS was checked and adjusted at around 1.1 m3/min,
and complied with the range specified in the Updated EM&A Manual for HKLR
(Version 1.0) (i.e. 0.6-1.7 m3/min).
(x) The programmable digital timer was set for a sampling period of 24 hours,
and the starting time, weather condition and the filter number were recorded.
(xi) The initial elapsed time was recorded.
(xii) At the end of sampling, on site temperature and atmospheric pressure
readings were taken and the final flow rate of the HVS was checked and
recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully and folded in half length so
that only surfaces with collected particulate matter were in contact.
(xv)
It was then placed in a clean plastic envelope and sealed.
(xvi) All monitoring information was recorded on a standard data sheet.
(xvii) Filters were then sent to ALS Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance and Calibration
(i) The HVS and its accessories were maintained in good working condition,
such as replacing motor brushes routinely and checking electrical wiring to ensure
a continuous power supply.
(ii) 5-point calibration of the HVS was conducted using TE-5025A Calibration Kit prior to the
commencement of baseline monitoring. Bi-monthly 5-point calibration of the HVS
will be carried out during impact monitoring.
(iii) Calibration certificate of the HVSs are provided in Appendix C.
2.5.2 1-hour TSP
Monitoring
(a) Measuring Procedures
The measuring procedures of
the 1-hour dust meter were in accordance with the Manufacturerˇ¦s Instruction
Manual as follows:-
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the ˇ§TIME SETTINGˇ¨ switch to [BG].
(iv)
Push ˇ§START/STOPˇ¨ switch to perform background measurement for 6
seconds.
(v)
Turn the knob at SENSI ADJ position to insert the light scattering
plate.
(vi)
Leave the equipment for 1 minute upon ˇ§SPAN CHECKˇ¨ is indicated in the
display.
(vii)
Push ˇ§START/STOPˇ¨ switch to perform automatic sensitivity adjustment.
This measurement takes 1 minute.
(viii)
Pull out the knob and return it to MEASURE position.
(ix)
Push the ˇ§TIME SETTINGˇ¨ switch the time set in the display to 3 hours.
(x)
Lower down the air collection opening cover.
(xi)
Push ˇ§START/STOPˇ¨ switch to start measurement.
(b) Maintenance
and Calibration
(i) The 1-hour TSP meter
was calibrated at 1-year intervals against a Tisch Environmental Mass Flow
Controlled Total Suspended Particulate (TSP) High Volume Air Sampler.
Calibration certificates of the Laser Dust Monitors are provided in Appendix C.
2.6.1
The schedule for air quality monitoring in March 2018
is provided in Appendix D.
2.7.1
The monitoring results for
1-hour TSP and 24-hour TSP are summarized in Tables 2.6 and 2.7 respectively.
Detailed impact air quality monitoring results and relevant graphical plots are
presented in Appendix E.
Table 2.6 Summary
of 1-hour TSP Monitoring Results During the Reporting Month
Monitoring Station
|
Average (mg/m3)
|
Range (mg/m3)
|
Action Level (mg/m3)
|
Limit Level (mg/m3)
|
AMS5
|
37
|
7 ˇV 57
|
352
|
500
|
AMS6
|
33
|
19 ˇV 52
|
360
|
500
|
Table 2.7 Summary of 24-hour TSP Monitoring Results During the
Reporting Month
Monitoring Station
|
Average (mg/m3)
|
Range (mg/m3)
|
Action Level (mg/m3)
|
Limit Level (mg/m3)
|
AMS5
|
59
|
43 ˇV 94
|
164
|
260
|
AMS6
|
101
|
78 ˇV 169
|
173
|
260
|
2.7.2
No Action and Limit Level exceedances of 1-hr TSP were recorded at AMS5
and AMS6 during the reporting month. No Action and Limit Level exceedances of
24-hr TSP were recorded at AMS5 and AMS6 during the reporting month.
2.7.3 The event action plan
is annexed in Appendix F.
2.7.4
The
wind data obtained from the on-site weather station
during the reporting month is
shown in Appendix G.
3.1.1 In accordance with
the Contract Specific EM&A Manual, impact noise monitoring was conducted
for at least once per week during the construction phase of the Project. The
Action and Limit level of the noise monitoring is provided in Table 3.1.
Table 3.1 Action
and Limit Levels for Noise during Construction Period
Monitoring Station
|
Time Period
|
Action Level
|
Limit Level
|
NMS5 ˇV Ma Wan Chung
Village (Ma Wan Chung Resident Association) (Tung Chung)
|
0700-1900 hours on normal
weekdays
|
When one documented
complaint is received
|
75 dB(A)
|
3.2.1 Noise monitoring was
performed using sound level meters at each designated monitoring station. The sound level meters deployed comply
with the International Electrotechnical Commission Publications (IEC) 651:1979
(Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator was deployed to
check the sound level meters at a known sound pressure level. Brand and model of the equipment are
given in Table 3.2.
Table 3.2 Noise
Monitoring Equipment
Equipment
|
Brand and Model
|
Integrated Sound Level
Meter
|
B&K 2238
|
Acoustic Calibrator
|
B&K 4231
|
3.3.1
Monitoring location NMS5 was set up at the
proposed locations in accordance with Contract Specific EM&A Manual.
3.3.2
Figure 2.1 shows the locations
of monitoring stations. Table 3.3 describes the details of the monitoring
stations.
Table 3.3 Locations
of Impact Noise Monitoring Stations
Monitoring Station
|
Location
|
NMS5
|
Ma Wan Chung Village (Ma
Wan Chung Resident Association) (Tung Chung)
|
3.4.1
Table 3.4 summarizes the
monitoring parameters, frequency and duration of impact noise monitoring.
Table 3.4 Noise
Monitoring Parameters, Frequency and Duration
Parameter
|
Frequency and Duration
|
30-mins measurement at
each monitoring station between 0700 and 1900 on normal weekdays (Monday to
Saturday). Leq, L10 and L90 would be
recorded.
|
At least once per week
|
3.5.1
Monitoring Procedure
(a) The sound level meter was
set on a tripod at a height of 1.2 m
above the podium for free-field
measurements at NMS5. A correction of +3 dB(A) shall be made to
the free field measurements.
(b)
The battery condition was
checked to ensure the correct functioning of the meter.
(c)
Parameters such as
frequency weighting, the time weighting and the measurement time were set as
follows:-
(i) frequency weighting:
A
(ii) time weighting: Fast
(iii) time
measurement: Leq(30-minutes) during non-restricted hours i.e. 07:00
ˇV 1900 on normal weekdays
(d)
Prior to and after each
noise measurement, the meter was calibrated using the acoustic calibrator for
94.0 dB(A) at 1000 Hz. If the
difference in the calibration level before and after measurement was more than
1.0 dB(A), the measurement would be considered invalid and repeat of noise
measurement would be required after re-calibration or repair of the equipment.
(e)
During the monitoring
period, the Leq, L10 and L90 were
recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
(f)
Noise measurement was
paused during periods of high intrusive noise (e.g. dog barking, helicopter
noise) if possible. Observations were recorded when intrusive noise was
unavoidable.
(g)
Noise monitoring was
cancelled in the presence of fog, rain, wind with a steady speed exceeding 5m/s, or wind with gusts exceeding 10m/s. The wind speed shall be checked
with a portable wind speed meter capable of measuring the wind speed in m/s.
3.5.2
Maintenance and Calibration
(a) The microphone head of the sound level
meter was cleaned with soft cloth at regular intervals.
(b) The meter and calibrator
were sent to the supplier or HOKLAS laboratory to check and calibrate at yearly
intervals.
(c) Calibration certificates
of the sound level meters and acoustic calibrators are provided in Appendix C.
3.6.1 The schedule for construction
noise monitoring in March 2018 is provided in Appendix D.
3.7.1 The monitoring
results for construction noise are summarized in Table 3.5 and the monitoring results and relevant graphical plots
are provided in Appendix E.
Table 3.5 Summary
of Construction Noise Monitoring Results During the Reporting Month
Monitoring Station
|
Average Leq (30 mins), dB(A)
|
Range of Leq (30 mins), dB(A)
|
Limit Level Leq (30 mins), dB(A)
|
NMS5
|
59
|
59 ˇV 60
|
75
|
3.7.2 There were no Action and Limit
Level exceedances for noise during daytime on normal weekdays of the reporting month.
3.7.3 Major noise sources
during the noise monitoring included construction activities of the Contract and nearby traffic.
3.7.4
The event action plan is annexed in Appendix F.
4
Water Quality Monitoring
4.1.1
Impact water quality monitoring was carried out to
ensure that any deterioration of water quality is detected, and that timely
action is taken to rectify the situation.
For impact water quality monitoring, measurements were taken in
accordance with the Contract Specific EM&A Manual. Table 4.1 shows the established Action/Limit Levels for the
environmental monitoring works. The ET proposed to amend the Acton Level
and Limit Level for turbidity and suspended solid and EPD approved ETˇ¦s
proposal on 25 March 2013. Therefore,
Action Level and Limit Level for the Contract have been changed since 25 March
2013.
4.1.2
The original and revised Action Level and
Limit Level for turbidity and suspended solid are shown in Table 4.1.
Table 4.1 Action
and Limit Levels for Water Quality
Parameter (unit)
|
Water Depth
|
Action Level
|
Limit Level
|
Dissolved Oxygen (mg/L) (surface,
middle and bottom)
|
Surface and Middle
|
5.0
|
4.2 except 5 for Fish
Culture Zone
|
Bottom
|
4.7
|
3.6
|
Turbidity (NTU)
|
Depth average
|
27.5 or 120% of upstream
control stationˇ¦s turbidity at the same tide of the same day;
The action level has been
amended to ˇ§27.5 and 120% of upstream control stationˇ¦s turbidity at the same
tide of the same dayˇ¨ since 25 March 2013.
|
47.0 or 130% of turbidity
at the upstream control station at the same tide of same day;
The limit level has been amended
to ˇ§47.0 and 130% of turbidity at the upstream control station at the
same tide of same dayˇ¨ since 25 March 2013.
|
Suspended Solid (SS)
(mg/L)
|
Depth average
|
23.5 or 120% of upstream
control stationˇ¦s SS at the same tide of the same day;
The action level has been
amended to ˇ§23.5 and 120% of upstream control stationˇ¦s SS at the same tide of
the same dayˇ¨ since 25 March 2013.
|
34.4 or 130% of SS at the
upstream control station at the same tide of same day and 10mg/L for Water
Services Department Seawater Intakes;
The limit level has been
amended to ˇ§34.4 and 130% of SS at the upstream control station at the same
tide of same day and 10mg/L for Water Services Department Seawater Intakesˇ¨
since 25 March 2013
|
Notes:
(1) Depth-averaged
is calculated by taking the arithmetic means of reading of all three depths.
(2) For DO,
non-compliance of the water quality limit occurs when monitoring result is
lower that the limit.
(3) For SS &
turbidity non-compliance of the water quality limits occur when monitoring
result is higher than the limits.
(4) The change to
the Action and limit Levels for Water Quality Monitoring for the EM&A works
was approved by EPD on 25 March 2013.
4.2.1 Table 4.2 summarizes the
equipment used in the impact water quality monitoring programme.
Table 4.2 Water
Quality Monitoring Equipment
Equipment
|
Brand and Model
|
DO and Temperature Meter,
Salinity Meter, Turbidimeter and pH Meter
|
YSI Model 6820
|
Positioning Equipment
|
JRC DGPS 224 Model
JLR-4341 with J-NAV 500 Model NWZ4551
|
Water Depth Detector
|
Eagle Cuda-168 and
Lowrance x-4
|
Water Sampler
|
Kahlsio Water Sampler
(Vertical) 2.2 L with messenger
|
4.3.1 Table 4.3 summarizes the monitoring parameters, frequency and
monitoring depths of impact water quality monitoring as required in the Contract
Specific EM&A Manual.
Table 4.3 Impact
Water Quality Monitoring Parameters and Frequency
Monitoring Stations
|
Parameter, unit
|
Frequency
|
No. of depth
|
Impact Stations:
IS5, IS(Mf)6, IS7, IS8, IS(Mf)9 & IS10,
Control/Far Field
Stations:
CS2 & CS(Mf)5,
Sensitive Receiver
Stations:
SR3, SR4, SR5, SR10A & SR10B
|
ˇP
Depth, m
ˇP
Temperature, oC
ˇP
Salinity, ppt
ˇP
Dissolved Oxygen
(DO), mg/L
ˇP
DO Saturation, %
ˇP
Turbidity, NTU
ˇP
pH
ˇP Suspended Solids (SS), mg/L
|
Three times per week
during mid-ebb and mid-flood tides (within ˇÓ 1.75 hour of the predicted time)
|
3
(1 m below water surface,
mid-depth and 1 m above sea bed, except where the water depth is less than 6
m, in which case the mid-depth station may be omitted. Should the water depth
be less than 3 m, only the mid-depth station will be monitored).
|
4.4.1
In accordance with the Contract Specific EM&A Manual, thirteen
stations (6 Impact Stations, 5 Sensitive Receiver Stations and 2 Control Stations) were
designated for impact water quality monitoring. The six Impact Stations (IS) were chosen
on the basis of their proximity to the reclamation and thus the greatest
potential for water quality impacts, the five Sensitive Receiver Stations (SR)
were chosen as they are close to the key sensitive receives and the two Control
Stations (CS) were chosen to facilitate comparison of the water quality of the
IS stations with less influence by the Project/ ambient water quality
conditions.
4.4.2
A new water quality monitoring team has been employed for carrying out
water quality monitoring work for the Contract starting from 23 August 2017. Due
to marine work of the Expansion of Hong Kong International Airport into a
Three-Runway System (3RS Project), original locations of water quality
monitoring stations CS2, SR5 and IS10 are enclosed by works boundary of 3RS
Project. Alternative impact water quality monitoring stations, naming as
CS2(A), SR5(N) and IS10(N) was approved on 28 July 2017 and were adopted
starting from 23 August 2017 to replace the original locations of water quality
monitoring for the Contract.
4.4.3
The topographical condition of the water monitoring stations SR3 (Coordinate:
810525E, 816456N), SR4 (Coordinate: 814760E, 817867N), SR10A (Coordinate:
823741E, 823495N) and SR10B (Coordinate: 823686E, 823213N) cannot be accessed
safely for undertaking water quality monitoring. The water quality monitoring has
been temporarily conducted at alternative stations, namely SR3(N) (Coordinate
810689E, 816591N), SR4(N) (Coordinate: 814705E, 817859N) and SR10A(N)
(Coordinate: 823644E, 823484N) since 1 September 2017. The water quality
monitoring at station SR10B was temporarily conducted at Coordinate: 823683E,
823187N on 1, 4, 6, 8 September 2017 and has been temporarily fine-tuned to
alternative station SR10B(N2) (Coordinate: 823689E, 823159N) since 11 September
2017. Proposal for permanently relocating the aforementioned stations was
approved by EPD on 8 January 2018.
4.4.4
The locations of water quality monitoring stations
during the reporting period are summarized in Table 4.4 and shown in Figure 2.1.
Table 4.4 Impact
Water Quality Monitoring Stations
Monitoring Stations
|
Description
|
Coordinates
|
Easting
|
Northing
|
IS5
|
Impact Station (Close to
HKLR construction site)
|
811579
|
817106
|
IS(Mf)6
|
Impact Station (Close to
HKLR construction site)
|
812101
|
817873
|
IS7
|
Impact Station (Close to
HKBCF construction site)
|
812244
|
818777
|
IS8
|
Impact Station (Close to
HKBCF construction site)
|
814251
|
818412
|
IS(Mf)9
|
Impact Station (Close to
HKBCF construction site)
|
813273
|
818850
|
IS10(N)
|
Impact Station (Close to
HKBCF construction site)
|
812942
|
820881
|
SR3(N)
|
Sensitive receivers (San
Tau SSSI)
|
810689
|
816591
|
SR4(N)
|
Sensitive receivers (Tai
Ho Inlet)
|
814705
|
817859
|
SR5(N)
|
Sensitive Receivers
(Artificial Reef in NE Airport)
|
812569
|
821475
|
SR10A(N)
|
Sensitive receivers (Ma
Wan Fish Culture Zone)
|
823644
|
823484
|
SR10B(N2)
|
Sensitive receivers (Ma
Wan Fish Culture Zone)
|
823689
|
823159
|
CS2(A)
|
Control Station (Mid-Ebb)
|
805232
|
818606
|
CS(Mf)5
|
Control Station
(Mid-Flood)
|
817990
|
821129
|
|
4.5
Monitoring
Methodology
4.5.1 Instrumentation
(a) The
in-situ water quality parameters including dissolved oxygen, temperature,
salinity and turbidity, pH were measured by multi-parameter meters.
4.5.2 Operating/Analytical
Procedures
(a) Digital Differential Global Positioning Systems
(DGPS) were used to ensure that the correct location was selected prior to
sample collection.
(b) Portable, battery-operated echo sounders were used
for the determination of water depth at each designated monitoring station.
(c) All in-situ measurements were taken at 3 water
depths, 1 m below water surface, mid-depth and 1 m above sea bed, except where
the water depth was less than 6 m, in which case the mid-depth station was
omitted. Should the water depth be less than 3 m, only the mid-depth station
was monitored.
(d) At each measurement/sampling depth, two consecutive
in-situ monitoring (DO concentration and saturation, temperature, turbidity,
pH, salinity) and water sample for SS. The probes were retrieved out of the
water after the first measurement and then re-deployed for the second
measurement. Where the difference in the value between the first and second
readings of DO or turbidity parameters was more than 25% of the value of the
first reading, the reading was discarded and further readings were taken.
(e) Duplicate samples from each independent sampling
event were collected for SS measurement. Water samples were collected using the
water samplers and the samples were stored in high-density polythene bottles.
Water samples collected were well-mixed in the water sampler prior to
pre-rinsing and transferring to sample bottles. Sample bottles were pre-rinsed
with the same water samples. The sample bottles were then be packed in
cool-boxes (cooled at 4oC without being frozen), and delivered to
ALS Technichem (HK) Pty Ltd. for the analysis of suspended solids
concentrations. The laboratory determination work would be started within 24
hours after collection of the water samples. ALS Technichem (HK) Pty Ltd. is a
HOKLAS accredited laboratory and has comprehensive quality assurance and
quality control programmes.
(f) The analysis method and detection limit for SS is
shown in Table 4.5.
Table 4.5 Laboratory Analysis for Suspended
Solids
Parameters
|
Instrumentation
|
Analytical Method
|
Detection Limit
|
Suspended Solid (SS)
|
Weighting
|
APHA 2540-D
|
0.5mg/L
|
(g) Other relevant data were recorded, including
monitoring location / position, time, water depth, tidal stages, weather
conditions and any special phenomena or work underway at the construction site
in the field log sheet for information.
4.5.3 Maintenance and
Calibrations
(a) All in situ monitoring
instruments would be calibrated by ALS Technichem (HK) Pty Ltd. before use and
at 3-monthly intervals throughout all stages of the water quality monitoring
programme. The procedures of performance check of sonde and testing results are
provided in Appendix C.
4.6.1
The schedule for impact water quality monitoring in March 2018 is provided in Appendix D.
4.7.1 Impact water quality
monitoring was conducted at all designated monitoring stations during the
reporting month. Impact water quality monitoring results and relevant graphical
plots are provided in Appendix E.
4.7.2
Water quality impact sources during water quality monitoring were the
construction activities of the Contract, nearby construction activities by
other parties and nearby operating vessels by other parties.
4.7.3 For marine water quality monitoring, no Action Level and Limit Level
exceedances of dissolved oxygen level and turbidity level were recorded during
the reporting month. No Limit Level exceedances of suspended solids level were
recorded during the reporting month. Two Action Level exceedances of suspended
solids level were recorded during the reporting month. Number of exceedances recorded
during the reporting month at each impact station are summarized in Table 4.6.
Table 4.6 Summary of Water Quality
Exceedances
Station
|
Exceedance Level
|
DO
(S&M)
|
DO
(Bottom)
|
Turbidity
|
SS
|
Total number of exceedances
|
Ebb
|
Flood
|
Ebb
|
Flood
|
Ebb
|
Flood
|
Ebb
|
Flood
|
Ebb
|
Flood
|
IS5
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
IS(Mf)6
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
IS7
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
IS8
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
23-3-2018
|
0
|
1
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
IS(Mf)9
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
IS10(N)
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
SR3(N)
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
21-3-2018
|
0
|
1
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
SR4(N)
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
SR5(N)
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
SR10A(N)
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
SR10B(N2)
|
Action Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Limit Level
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
--
|
0
|
0
|
Total
|
Action
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
2
|
2**
|
Limit
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0
|
0**
|
Notes:
S: Surface;
M: Mid-depth;
** The
total number of
exceedances
4.7.4
The exceedances of suspended
solids level recorded during reporting period were considered to be attributed
to other external factors such as sea condition, rather than the contract
works. Therefore, the exceedances were considered as non-contract related.
Records of ˇ§Notification of Environmental Quality Limit Exceedancesˇ¨ are provided
in Appendix N.
4.7.5 The event action plan is annexed
in Appendix F.
5.1.1
Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to
evaluate whether there have
been any effects on the
dolphins.
5.1.2
The Action Level and Limit Level for dolphin monitoring are shown in Table 5.1.
Table
5.1 Action
and Limit Levels for Dolphin Monitoring
|
North Lantau Social Cluster
|
NEL
|
NWL
|
Action
Level
|
STG < 4.2 & ANI < 15.5
|
STG < 6.9 & ANI <
31.3
|
Limit Level
|
(STG < 2.4 & ANI
< 8.9) and (STG < 3.9 & ANI < 17.9)
|
Remarks:
1. STG means quarterly encounter rate of number of dolphin sightings.
2. ANI means quarterly encounter rate of total number of dolphins.
3. For North Lantau Social Cluster, AL will be trigger if either NEL or NWL fall below the criteria; LL will
be triggered if both NEL and NWL
fall below the criteria.
5.1.3 The revised Event and Action Plan
for dolphin Monitoring was approved by EPD in 6 May 2013. The revised Event and Action
Plan is annexed in Appendix F.
Vessel-based Line-transect Survey
5.2.1
According to the
requirement of the updated EM&A manual, dolphin monitoring programme should
cover all transect lines in NEL and NWL survey areas (see Figure 1 of Appendix H) twice per
month throughout the entire construction period. The co-ordinates of all transect lines
are shown in Table 5.2. The
coordinates of several starting and ending points have been revised due to the
presence of a work zone to the north of the airport platform with intense
construction activities in association with the construction of the third
runway expansion for the Hong Kong International Airport. The EPD issued a memo and confirmed that
they had no objection on the revised transect lines on 28 July 2017, and the
revised coordinates are in red and marked with an asterisk in Table 5.2.
Table 5.2 Co-ordinates
of Transect Lines
Line No.
|
Easting
|
Northing
|
|
Line No.
|
Easting
|
Northing
|
1
|
Start Point
|
804671
|
815456
|
|
13
|
Start Point
|
816506
|
819480
|
1
|
End Point
|
804671
|
831404
|
|
13
|
End Point
|
816506
|
824859
|
2
|
Start Point
|
805476
|
820800*
|
|
14
|
Start Point
|
817537
|
820220
|
2
|
End Point
|
805476
|
826654
|
|
14
|
End Point
|
817537
|
824613
|
3
|
Start Point
|
806464
|
821150*
|
|
15
|
Start Point
|
818568
|
820735
|
3
|
End Point
|
806464
|
822911
|
|
15
|
End Point
|
818568
|
824433
|
4
|
Start Point
|
807518
|
821500*
|
|
16
|
Start Point
|
819532
|
821420
|
4
|
End Point
|
807518
|
829230
|
|
16
|
End Point
|
819532
|
824209
|
5
|
Start Point
|
808504
|
821850*
|
|
17
|
Start Point
|
820451
|
822125
|
5
|
End Point
|
808504
|
828602
|
|
17
|
End Point
|
820451
|
823671
|
6
|
Start Point
|
809490
|
822150*
|
|
18
|
Start Point
|
821504
|
822371
|
6
|
End Point
|
809490
|
825352
|
|
18
|
End Point
|
821504
|
823761
|
7
|
Start Point
|
810499
|
822000*
|
|
19
|
Start Point
|
822513
|
823268
|
7
|
End Point
|
810499
|
824613
|
|
19
|
End Point
|
822513
|
824321
|
8
|
Start Point
|
811508
|
821123
|
|
20
|
Start Point
|
823477
|
823402
|
8
|
End Point
|
811508
|
824254
|
|
20
|
End Point
|
823477
|
824613
|
9
|
Start Point
|
812516
|
821303
|
|
21
|
Start Point
|
805476
|
827081
|
9
|
End Point
|
812516
|
824254
|
|
21
|
End Point
|
805476
|
830562
|
10
|
Start Point
|
813525
|
821176
|
|
22
|
Start Point
|
806464
|
824033
|
10
|
End Point
|
813525
|
824657
|
|
22
|
End Point
|
806464
|
829598
|
11
|
Start Point
|
814556
|
818853
|
|
23
|
Start Point
|
814559
|
821739
|
11
|
End Point
|
814556
|
820992
|
|
23
|
End Point
|
814559
|
824768
|
12
|
Start Point
|
815542
|
818807
|
|
24*
|
Start Point
|
805476*
|
815900*
|
12
|
End Point
|
815542
|
824882
|
|
24*
|
End Point
|
805476*
|
819100*
|
Note:
Co-ordinates in red and marked with asterisk are revised co-ordinates of
transect line.
5.2.2
The survey team used standard line-transect methods
(Buckland et al. 2001) to conduct the systematic vessel surveys, and followed
the same technique of data collection that has been adopted over the last 20
years of marine mammal monitoring surveys in Hong Kong developed by HKCRP (see
Hung 2017). For each monitoring
vessel survey, a 15-m inboard vessel with an open upper deck (about 4.5 m above
water surface) was used to make observations from the flying bridge area.
5.2.3
Two experienced observers (a data recorder and a
primary observer) made up the on-effort survey team, and the survey vessel
transited different transect lines at a constant speed of 13-15 km per
hour. The data recorder searched
with unaided eyes and filled out the datasheets, while the primary observer
searched for dolphins and porpoises continuously through 7 x 50 Fujinon marine binoculars. Both observers searched the sea ahead of
the vessel, between 270o and 90o (in relation to the bow,
which is defined as 0o).
One to two additional experienced observers were available on the boat
to work in shift (i.e. rotate every 30 minutes) in order to minimize fatigue of
the survey team members. All
observers were experienced in small cetacean survey techniques and identifying
local cetacean species.
5.2.4
During on-effort survey periods, the survey team
recorded effort data including time, position (latitude and longitude), weather
conditions (Beaufort sea state and visibility), and distance traveled in each
series (a continuous period of search effort) with the assistance of a handheld
GPS (Garmin eTrex Legend).
5.2.5
Data including time, position and vessel speed were
also automatically and continuously logged by handheld GPS throughout the
entire survey for subsequent review.
5.2.6
When dolphins were sighted, the survey team would
end the survey effort, and immediately record the initial sighting distance and
angle of the dolphin group from the survey vessel, as well as the sighting time
and position. Then the research vessel
was diverted from its course to approach the animals for species
identification, group size estimation, assessment of group composition, and
behavioural observations. The
perpendicular distance (PSD) of the dolphin group to the transect line was later
calculated from the initial sighting distance and angle.
5.2.7
Survey effort being conducted along the parallel
transect lines that were perpendicular to the coastlines (as indicated in Figure 1 of Appendix H) was
labeled as ˇ§primaryˇ¨ survey effort, while the survey effort conducted along the
connecting lines between parallel lines was labeled as ˇ§secondaryˇ¨ survey
effort. According to HKCRP
long-term dolphin monitoring data, encounter rates of Chinese white dolphins
deduced from effort and sighting data collected along primary and secondary
lines were similar in NEL and NWL survey areas. Therefore, both primary and secondary
survey effort were presented as on-effort survey effort in this report.
5.2.8
Encounter rates of Chinese white dolphins (number
of on-effort sightings per 100 km of survey effort and number of dolphins from
all on-effort sightings per 100 km of survey effort) were calculated in NEL and
NWL survey areas in relation to the amount of survey effort conducted during
each month of monitoring survey.
Only data collected under Beaufort 3 or below condition would be used
for encounter rate analysis.
Dolphin encounter rates were calculated using primary survey effort
alone, as well as the combined survey effort from both primary and secondary
lines.
Photo-identification Work
5.2.9
When a group of Chinese White Dolphins were sighted
during the line-transect survey, the survey team would end effort and approach
the group slowly from the side and behind to take photographs of them. Every attempt was made to photograph
every dolphin in the group, and even photograph both sides of the dolphins,
since the colouration and markings on both sides may not be symmetrical.
5.2.10
A professional digital camera (Canon EOS 7D model), equipped with long telephoto lenses (100-400
mm zoom), were available on board for researchers to take sharp, close-up
photographs of dolphins as they surfaced.
The images were shot at the highest available resolution and stored on
Compact Flash memory cards for downloading onto a computer.
5.2.11
All digital images taken in the field were first
examined, and those containing potentially identifiable individuals were sorted
out. These photographs would then
be examined in greater detail, and were carefully compared to the existing
Chinese White Dolphin photo-identification catalogue maintained by HKCRP since
1995.
5.2.12
Chinese White Dolphins can be identified by their
natural markings, such as nicks, cuts, scars and deformities on their dorsal
fin and body, and their unique spotting patterns were also used as secondary
identifying features (Jefferson 2000).
5.2.13 All
photographs of each individual were then compiled and arranged in chronological
order, with data including the date and location first identified (initial
sighting), re-sightings, associated dolphins, distinctive features, and age
classes entered into a computer database.
Detailed information on all identified individuals will be further
presented as an appendix in quarterly EM&A reports.
Vessel-based Line-transect Survey
5.3.1
During the month of March 2018, two sets of systematic line-transect vessel
surveys were conducted on the 8th, 12th, 20th
and 23rd to cover all transect lines in NWL and NEL
survey areas twice. The survey
routes of each survey day are presented in Figures
2 to 5 of Appendix
H.
5.3.2
From these surveys, a total of 263.34 km of survey effort was collected, 85.3% of the total survey effort being conducted under favourable weather
conditions (i.e. Beaufort Sea State 3 or below with good visibility) (Annex I of Appendix H). Among the two survey areas, 98.00 km and 165.34 km of survey effort were collected from NEL and
NWL survey areas respectively. Moreover, the total survey effort conducted on primary
lines was 192.21 km, while the effort on secondary lines was 71.13 km .
5.3.3
During the two sets of monitoring in March 2018, six groups of 26 Chinese
White Dolphins were sighted (see Annex II of Appendix H). All dolphin sightings were made in NWL, while none
was sighted in NEL. Moreover, all six dolphin groups were sighted on
primary lines during on-effort search (Annex II of Appendix H). Notably, none of the dolphin groups was associated with any operating fishing vessel.
5.3.4
Distribution of the six dolphin sightings made in March 2018 is shown in Figure 6 of Appendix H. Three of them were sighted along the western end of
the Sha Chau and Lung Kwu Chau Marine Park boundary, while another three groups
were sighted between Lung Kwu Chau and Black Point (Figure 6 of Appendix H).
5.3.5
Notably, all
dolphin groups were sighted far away from the HKLR03/HKBCF reclamation sites as
well as the HKLR09/TMCLKL alignments (Figure 6 of Appendix H).
5.3.6
During the Marchˇ¦s
surveys, encounter rates of Chinese White Dolphins deduced from the survey
effort and on-effort sighting data made under favourable conditions (Beaufort 3
or below) are shown in Tables
5.3 and 5.4.
Table 5.3 Individual Survey Event
Encounter Rates
|
Encounter
rate (STG)
(no. of on-effort dolphin sightings per 100
km of survey effort)
|
Encounter
rate (ANI)
(no. of dolphins from all on-effort
sightings per 100 km of survey effort)
|
Primary Lines Only
|
Primary Lines Only
|
NEL
|
Set
1: March 8th / 12th
|
0.0
|
0.0
|
Set
2: March 20th / 23rd
|
0.0
|
0.0
|
NWL
|
Set
1: March 8th / 12th
|
1.7
|
5.2
|
Set
2: March 20th / 23rd
|
12.3
|
56.7
|
Remark:
1. Dolphin Encounter Rates Deduced from the Two
Sets of Surveys (Two Surveys in Each Set) in March 2018 in Northeast Lantau
(NEL) and Northwest Lantau (NWL).
Table 5.4 Monthly
Average Encounter Rates
|
Encounter rate (STG)
(no.
of on-effort dolphin sightings per 100 km of survey effort)
|
Encounter rate (ANI)
(no.
of dolphins from all on-effort sightings per 100 km of survey effort)
|
Primary Lines Only
|
Both Primary and Secondary Lines
|
Primary Lines Only
|
Both Primary and Secondary Lines
|
Northeast
Lantau
|
0.0
|
0.0
|
0.0
|
0.0
|
Northwest
Lantau
|
6.1
|
4.6
|
26.4
|
19.8
|
Remark:
1.
Monthly Average Dolphin Encounter Rates (Sightings Per 100 km of
Survey Effort) from All Four Surveys Conducted in March 2018 on Primary Lines only as well as Both Primary
Lines and Secondary Lines in Northeast Lantau (NEL) and Northwest Lantau (NWL).
5.3.7
The average dolphin group size in March 2018 was 4.3 individuals per
group, which was higher than the averages in the previous monitoring
months. All except one group were
composed of small groups of 3-4 animals only, while a large group of 12 animals
was sighted to the west of Lung Kwu Chau (Annex
II of Appendix H).
Photo-identification Work
5.3.8
Twelve known individual
dolphins were sighted 12 times during the Marchˇ¦s surveys (Annexes III and IV of Appendix H), and all of them were re-sighted
only once during the monthly surveys.
5.3.9
Notably, during their re-sightings in March 2018, two individuals (WL145 and WL179) were sighted with their young
calves.
Conclusion
5.3.10
During this month of dolphin monitoring, no adverse impact from the
activities of this construction project on Chinese White Dolphins was
noticeable from general observations.
5.3.11
Due to monthly variation in dolphin occurrence within the study area, it
would be more appropriate to draw conclusion on whether any impacts on dolphins
have been detected related to the construction activities of this project in
the quarterly EM&A report, where comparison on distribution, group size and
encounter rates of dolphins between the quarterly impact monitoring period (March
- May 2018) and baseline monitoring period (3-month period) will be made.
5.4.1 Buckland,
S. T., Anderson, D. R., Burnham, K. P., Laake, J. L., Borchers, D. L., and
Thomas, L. 2001. Introduction to distance sampling:
estimating abundance of biological populations. Oxford University Press, London.
5.4.2 Hung,
S. K. 2017. Monitoring of Marine Mammals in Hong
Kong waters: final report (2016-17).
An unpublished report submitted to the Agriculture, Fisheries and
Conservation Department, 162 pp.
5.4.3 Jefferson, T. A. 2000. Population biology of the Indo-Pacific
hump-backed dolphin in Hong Kong waters.
Wildlife Monographs 144:1-65.
Methodology
6.1.1 To avoid disturbance
to the mudflat and nuisance to navigation, no fixed marker/monitoring rod was
installed at the monitoring stations. A high precision Global Navigation
Satellite System (GNSS) real time location fixing system (or equivalent
technology) was used to locate the station in the precision of 1mm, which is
reasonable under flat mudflat topography with uneven mudflat surface only at
micro level. This method has been
used on Agricultural Fisheries and Conservation Departmentˇ¦s (AFCD) project, namely
Baseline Ecological Monitoring Programme for the Mai Po Inner Deep Bay Ramsar
Site for measurement of seabed levels.
6.1.2 Measurements were
taken directly on the mudflat surface. The Real Time Kinematic GNSS (RTK GNSS)
surveying technology was used to measure mudflat surface levels and 3D
coordinates of a survey point. The
RTK GNSS survey was calibrated against a reference station in the field before
and after each survey. The
reference station is a survey control point established by the Lands Department
of the HKSAR Government or traditional land surveying methods using
professional surveying instruments such as total station, level and/or geodetic
GNSS. The coordinates system was in
HK1980 GRID system. For this
contract, the reference control station was surveyed and established by
traditional land surveying methods using professional surveying instruments
such as total station, level and RTK GNSS.
The accuracy was down to mm level so that the reference control station
has relatively higher accuracy. As
the reference control station has higher accuracy, it was set as true
evaluation relative to the RTK GNSS measurement. All position and height correction were
adjusted and corrected to the reference control station. Reference station survey result and
professional land surveying calibration is shown as Table 6.1:
Table 6.1 Reference
Station Survey result and GNSS RTK calibration result of Round 1
Reference Station
|
Easting (m)
|
Northing (m)
|
Baseline reference elevation (mPD) (A)
|
Round 1 Survey (mPD) (B)
|
Calibration Adjustment (B-A)
|
T1
|
811248.660mE
|
816393.173mN
|
3.840
|
3.817
|
-0.023
|
T2
|
810806.297mE
|
815691.822mN
|
4.625
|
4.653
|
+0.028
|
T3
|
810778.098mE
|
815689.918mN
|
4.651
|
4.660
|
+0.009
|
T4
|
810274.783mE
|
816689.068mN
|
2.637
|
2.709
|
+0.072
|
6.1.3 The precision of the
measured mudflat surface level reading (vertical precision setting) was within
10 mm (standard deviation) after averaging the valid survey records of the XYZ
HK1980 GRID coordinates. Each survey
record at each station was computed by averaging at least three measurements
that are within the above specified precision setting. Both digital data
logging and written records were collected in the field. Field data on station fixing and mudflat
surface measurement were recorded.
Monitoring Locations
6.1.4 Four monitoring
stations were established based on the site conditions for the sedimentation
monitoring and are shown in Figure 6.1.
Monitoring Results
6.1.5 The baseline
sedimentation rate monitoring was in September 2012 and impact sedimentation
rate monitoring was undertaken on 18 March 2018. The mudflat
surface levels at the four established monitoring stations and the
corresponding XYZ HK1980 GRID coordinates are presented in Table 6.2 and Table 6.3.
Table 6.2 Measured
Mudflat Surface Level Results
|
Baseline Monitoring
(September 2012)
|
Impact Monitoring
(March 2018)
|
Monitoring
Station
|
Easting
(m)
|
Northing
(m)
|
Surface
Level
(mPD)
|
Easting
(m)
|
Northing
(m)
|
Surface
Level
(mPD)
|
S1
|
810291.160
|
816678.727
|
0.950
|
810291.137
|
816678.716
|
1.181
|
S2
|
810958.272
|
815831.531
|
0.864
|
810958.257
|
815831.571
|
1.040
|
S3
|
810716.585
|
815953.308
|
1.341
|
810716.545
|
815953.375
|
1.518
|
S4
|
811221.433
|
816151.381
|
0.931
|
811221.422
|
816151.421
|
1.148
|
Table 6.3 Comparison
of measurement
|
Comparison of measurement
|
Remarks
and Recommendation
|
Monitoring Station
|
Easting (m)
|
Northing (m)
|
Surface Level
(mPD)
|
S1
|
-0.023
|
-0.011
|
0.231
|
Level continuously increased
|
S2
|
-0.015
|
0.040
|
0.176
|
Level continuously increased
|
S3
|
-0.040
|
0.067
|
0.177
|
Level continuously increased
|
S4
|
-0.011
|
0.040
|
0.217
|
Level continuously increased
|
6.1.6 This measurement result was
generally and relatively higher than the baseline measurement at S1, S2, S3 and
S4. The mudflat level is continuously increased.
6.2.1 The mudflat
monitoring covered water quality monitoring data. Reference was made to the water quality
monitoring data of the representative water quality monitoring station (i.e.
SR3(N)) as in the EM&A Manual.
The water quality monitoring location (SR3(N)) is shown in Figure 2.1.
6.2.2 Impact water quality
monitoring in San Tau (monitoring station SR3(N)) was conducted in March 2018. The monitoring parameters included
dissolved oxygen (DO), turbidity and suspended solids (SS).
6.2.3 The Impact
monitoring results for SR3(N) were extracted and summarised below:
Table 6.4 Impact
Water Quality Monitoring Results (Depth Average)
Date
|
Mid Ebb Tide
|
Mid Flood Tide
|
DO (mg/L)
|
Turbidity (NTU)
|
SS (mg/L)
|
DO (mg/L)
|
Turbidity (NTU)
|
SS (mg/L)
|
02-Mar-18
|
8.8
|
4.8
|
4.5
|
8.4
|
4.1
|
5.6
|
05-Mar-18
|
8.2
|
6.8
|
6.5
|
--
|
--
|
--
|
07-Mar-18
|
7.6
|
5.5
|
7.1
|
7.7
|
6.8
|
9.3
|
09-Mar-18
|
7.1
|
5.4
|
7.4
|
7.2
|
6.1
|
7.0
|
12-Mar-18
|
7.5
|
3.0
|
5.1
|
7.9
|
3.7
|
6.3
|
14-Mar-18
|
8.5
|
5.3
|
8.9
|
8.4
|
6.8
|
10.9
|
16-Mar-18
|
8.3
|
6.7
|
9.4
|
8.4
|
6.0
|
7.0
|
19-Mar-18
|
7.3
|
8.5
|
8.6
|
7.4
|
9.8
|
11.2
|
21-Mar-18
|
7.0
|
10.4
|
10.2
|
7.3
|
16.7
|
27.2
|
23-Mar-18
|
7.3
|
7.9
|
8.4
|
7.4
|
10.3
|
13.6
|
26-Mar-18
|
6.9
|
6.2
|
4.4
|
6.9
|
8.2
|
5.3
|
28-Mar-18
|
7.1
|
6.7
|
11.5
|
7.8
|
8.8
|
5.1
|
30-Mar-18
|
7.3
|
6.9
|
13.8
|
7.0
|
15.0
|
14.8
|
Average
|
7.6
|
6.5
|
8.1
|
7.7
|
8.5
|
10.3
|
Remark: Due to foggy weather and low visibility, water quality
monitoring at station SR3(N) during flood tide on 5 March 2018 were
cancelled.
|
Sampling Zone
6.3.1
In order to collect baseline
information of mudflats in the study site, the study site was divided into
three sampling zones (labeled as TC1, TC2, TC3) in Tung Chung Bay and one zone
in San Tau (labeled as ST) (Figure 2.1
of Appendix I). The horizontal shoreline of
sampling zones TC1, TC2, TC3 and ST were about 250 m, 300 m, 300 m and 250 m
respectively (Figure 2.2 of Appendix I).
Survey of horseshoe crabs, seagrass beds and intertidal communities were
conducted in every sampling zone. The present survey was conducted in March
2018 (totally 6 sampling days between 3rd and 21st March
2018).
6.3.2
Since the field survey of Jun. 2016, increasing number of trashes and
even big trashes (Figure 2.3 of Appendix I) were found in every sampling zone. It
raised a concern about the solid waste dumping and current-driven waste issues
in Tung Chung Wan. Respective measures (e.g. manual clean-up) should be
implemented by responsible units.
6.3.3
Similar to previous years,
large scaled recruitment of filamentious algae was observed at high shore
location in TC3 and ST (Figure 2.4 of
Appendix I). The algae had covered significant area of mudflat that might
affect the survey of horseshoe crab and seagrass
Horseshoe Crabs
6.3.4
Active search method was conducted for
horseshoe crab monitoring by two experienced surveyors in every sampling zone.
During the search period, any accessible and potential area would be
investigated for any horseshoe crab individuals within 2-3 hours of low tide
period (tidal level below 1.2 m above Chart Datum (C.D.)). Once a horseshoe
crab individual was found, the species was identified referencing to Li (2008).
The prosomal width, inhabiting substratum and respective GPS coordinate were
recorded. A photographic record was taken for future investigation. Any grouping behavior of individuals, if found, was recorded. The horseshoe crab surveys were
conducted on 14th (for TC3 and ST) and 21st (for TC1 and TC2)
March 2018. The weather was generally warm and humid on both field days without
rainfall.
6.3.5
In Jun. 2017, a big horseshoe crab was tangled by a trash gill net in ST
mudflat (Figure 2.3 of Appendix I). It was released to sea once after photo
recording. The horseshoe crab of such size should be inhabitating sub-tidal
environment while it forages on intertidal shore occasionally during high tide
period. If it is tangled by the trash net for few days, it may die due to
starvation or overheat during low tide period. These trash gill nets are
definitely ˇĄfatal trapˇ¦ for the horseshoe crabs and other marine life. Manual
clean-up should be implemented as soon as possible by responsible units.
Seagrass Beds
6.3.6
Active search method was conducted for seagrass bed monitoring by two
experienced surveyors in every sampling zone. During the search period, any
accessible and potential area would be investigated for any seagrass beds within
2-3 hours of low tide period. Once seagrass bed was found, the species,
estimated area, estimated coverage percentage and respective GPS coordinates
were recorded. The seagrass beds surveys were conducted on 14th (for
TC3 and ST) and 21st (for TC1 and TC2) March 2018. The weather was
generally warm and humid on both field days without rainfall.
Intertidal Soft Shore Communities
6.3.7 The
intertidal soft shore community surveys were conducted in low tide period on 3rd (for TC3), 4th
(for TC1), 11th (for TC2) and 17th (for ST) March 2018.
In every sampling zone, three 100m horizontal transect lines were laid at high tidal level (H: 2.0 m
above C.D.), mid tidal level (M: 1.5 m above
C.D.) and low tidal level (L: 1.0 m above C.D.). Along every horizontal transect line, ten random quadrats
(0.5 m x 0.5 m) were placed.
6.3.8 Inside
a quadrat, any visible epifauna were collected and were in-situ identified to
the lowest practical taxonomical resolution. Whenever possible a hand core
sample (10 cm internal diameter ´ 20 cm
depth) of sediments was collected in the quadrat. The core sample was gently
washed through a sieve of mesh size 2.0 mm in-situ. Any visible infauna were
collected and identified. Finally the top 5 cm surface sediments was dug for
visible infauna in the quadrat regardless of hand core sample was taken.
6.3.9 All collected fauna were released
after recording except some tiny individuals that are too small to be
identified on site. These tiny individuals were taken to laboratory for
identification under dissecting microscope.
6.3.10 The
taxonomic classification was conducted in accordance to the following
references: Polychaetes: Fauchald (1977), Yang and Sun (1988); Arthropods: Dai
and Yang (1991), Dong (1991); Mollusks: Chan and Caley (2003), Qi (2004).
Data Analysis
6.3.11 Data collected from
direct search and core sampling was pooled in every quadrat for data analysis.
Shannon-Weaver Diversity Index (Hˇ¦)
and Pielouˇ¦s Species Evenness (J)
were calculated for every quadrat using the formulae below,
Hˇ¦= -ŁU ( Ni / N ) ln ( Ni / N ) (Shannon and Weaver, 1963)
J = Hˇ¦ / ln S, (Pielou, 1966)
where S is the total number
of species in the sample, N is the total number of individuals, and Ni is the
number of individuals of the ith species.
6.4.1
In the event of the impact monitoring results
indicating that the density or the distribution pattern of intertidal fauna and
seagrass is found to be significant different to the baseline condition (taking
into account natural fluctuation in the occurrence and distribution pattern
such as due to seasonal change), appropriate actions should be taken and
additional mitigation measures should be implemented as necessary. Data should then be re-assessed and the
need for any further monitoring should be established. The action plan, as given in Table 6.5 should be undertaken within a
period of 1 month after a significant difference has been determined.
Table 6.5 Event
and Action Plan for Mudflat Monitoring
Event
|
ET Leader
|
IEC
|
SO
|
Contractor
|
Density or the
distribution pattern of horseshoe crab, seagrass or intertidal soft shore
communities recorded in the impact or post-construction monitoring are significantly lower than or different
from those recorded in the baseline monitoring.
|
Review historical data
to ensure differences are as a result of natural variation or previously
observed seasonal differences;
Identify source(s) of
impact;
Inform the IEC, SO and
Contractor;
Check monitoring data;
Discuss additional monitoring
and any other measures, with the IEC and Contractor.
|
Discuss monitoring with
the ET and the Contractor;
Review proposals for
additional monitoring and any other measures submitted by the Contractor and
advise the SO accordingly.
|
Discuss with the IEC
additional monitoring requirements and any other measures proposed by the ET;
Make agreement on the
measures to be implemented.
|
Inform the SO and in
writing;
Discuss with the ET and
the IEC and propose measures to the IEC and the ER;
Implement the agreed
measures.
|
Notes:
ET ˇV Environmental Team
IEC ˇV Independent
Environmental Checker
SO ˇV Supervising Officer
Horseshoe Crabs
6.5.1
In the
present survey, two species of horseshoe crab Carcinoscorpius rotundicauda (total 31 ind.) and Tachypleus tridentatus (total 44 ind.) were recorded. The recorded individuals were mainly
distributed along the shoreline from TC3 to ST. Grouping of 2-9 individuals was
usually observed on
similar substratum (fine sand or soft mud, slightly submerged).
Photo
records were shown in Figure 3.1 of Appendix
I while the complete survey records were listed in Annex II of Appendix I.
6.5.2
Table 3.1 of
Appendix I summarizes
the survey results of horseshoe crab in the present survey. For Carcinoscorpius rotundicauda, one individual was found in TC1
(prosomal width: 41.21 mm) only resulting in very low search record (0.3 ind. hr-1 person-1). In TC3, there was low-moderate number of individuals (22 ind.) with
average body size 55.27 mm (prosomal width ranged 26.63-93.88 mm). In ST, few individuals were found (8
ind.) with average body size 55.22 mm (35.18-66.75 mm). Both TC3 and ST were low in search record (1.3-3.7 ind. hr-1 person-1).
6.5.3
Similar survey results were found for Tachypleus tridentatus. One individual was found in TC1 (prosomal width: 39.61 mm) only
resulting in very low search record (0.3 ind. hr-1 person-1). In TC3, there was low-moderate number of individuals (31 ind.) with
average body size 55.83 mm (prosomal width ranged 38.90-85.36 mm). In ST, few individuals were found (12
ind.) with average body size 56.71 mm (39.63-87.61 mm). Both TC3 and ST were low in search record (2.0-5.2 ind. hr-1 person-1).
6.5.4
In the previous survey of Mar. 2015, there
was one important finding that a mating pair of Carcinoscorpius rotundicauda was found in ST (prosomal width: male
155.1 mm, female 138.2 mm) (Figure 3.2
of Appendix
I). It indicated
the importance of ST as a breeding ground of horseshoe crab. In Jun. 2017, mating pairs of Carcinoscorpius
rotundicauda were also found in TC2 (male 175.27 mm, female 143.51 mm) and
TC3 (male 182.08 mm, female 145.63 mm) (Figure 3.2 of Appendix I). In Dec. 2017 (present survey), one mating pair was of Carcinoscorpius rotundicauda was found
in TC3 (male 127.80 mm, female 144.61 mm) (Figure 3.2 of Appendix I). These mating pairs indicated that breeding of horseshoe crab could be
possible along the coast of Tung Chung Wan rather than ST only, as long as
suitable substratum was available. The recorded mating pairs were found nearly
burrowing in soft mud at low tidal level (0.5-1.0 m above C.D.). The smaller
male was holding the opisthosoma (abdomen carapace) of larger female from
behind. Moreover, suitable breeding period was believed in wet season (Mar -
Sep.) because tiny individuals (i.e. newly hatched) were usually recorded in
Jun. and Sep. every year.
6.5.5
In the previous surveys (Jun. 2016, Jun. -Dec.
2017), there were occasional records of large individuals of Carcinoscorpius rotundicauda (prosomal width
ranged 114.45- 178.67 mm,
either single or in pair) in ST (Figure
3.3 of Appendix I). Based on their sizes, it indicated that individuals of
prosomal width larger than 100 mm would progress its nursery stage from
intertidal habitat to sub-tidal habitat of Tung Chung Wan. These large
individuals might move onto intertidal shore occasionally during high tide for
foraging and breeding. Because they should be inhabiting sub-tidal habitat most
of the time. Their records were excluded from the data analysis to avoid mixing
up with juvenile population living on intertidal habitat.
6.5.6 No marked individual of horseshoe crab was
recorded in the present survey. Some marked individuals were found in the
previous surveys of Sep. 2013, Mar. 2014 and Sep. 2014. All of them were
released through a conservation programme in charged by Prof. Paul Shin
(Department of Biology and Chemistry, The City University of Hong Kong
(CityU)). It was a re-introduction trial of artificial bred horseshoe crab
juvenile at selected sites. So that the horseshoe crab population might be
restored in the natural habitat. Through a personal conversation with Prof.
Shin, about 100 individuals were released in the sampling zone ST on 20 June
2013. All of them were marked with color tape and internal chip detected by
specific chip sensor. There should be second round of release between June and
September 2014 since new marked individuals were found in the survey of Sep.
2014.
6.5.7 The artificial bred individuals, if found,
would be excluded from the results of present monitoring programme in order to
reflect the changes of natural population. However, the mark on their prosoma
might have been detached during moulting after a certain period of release. The
artificially released individuals were no longer distinguishable from the
natural population without the specific chip sensor. The survey data collected
would possibly cover both natural population and artificially bred individuals.
Population difference among the sampling
zones
6.5.8 Figures 3.4 and 3.5 of Appendix I show
the changes of number of individuals, mean prosomal width and search record of
horseshoe crabs Carcinoscorpius
rotundicauda and Tachypleus
tridentatus respectively in every sampling zone throughout the monitoring
period.
6.5.9 For TC3 and ST, medium to high
search records (i.e. number of individuals) of both species were always found
in wet season (Jun. and Sep.). The search record of ST was higher from Sep.
2012 to Jun. 2014 while it was replaced by TC3 from Sep. 2014 to Jun. 2015. The
search records were similar between two sampling zones from Sep. 2015 to Jun.
2016. In Sep. 2016, the search record of Carcinoscorpius
rotundicauda in ST was much higher than TC3. From Mar. to Jun. 2017, the
search records of both species were similar again between two sampling zones.
It showed a natural variation of horseshoe crab population in these two zones
due to weather condition and tidal effect. No obvious difference of horseshoe
crab population was noted between TC3 and ST. In Sep. 2017, the search records
of both horseshoe crab species decreased except the Carcinoscorpius rotundicauda in TC3. The survey results were
different from previous findings that there were usually higher search records
in Sep. One possible reason was that the serial cyclone hit decreased horseshoe
crab activity (totally 4 cyclone records between Jun. and Sep. 2017, to be
discussed in 'Seagrass survey' section). In Sep. 2017 and Mar. 2018 (present survey), higher search records were
found in TC3.
6.5.10 For TC1, the search record was at
low to medium level throughout the monitoring period. The change of Carcinoscorpius rotundicauda was relatively more variable than
that of Tachypleus
tridentatus. Relatively, the search record was very low in TC2 (2 ind. in Sep.
2013; 1 ind. in Mar.-Sep. 2014, Mar.-Jun. 2015; 4 ind. in Sep. 2015; 6 ind. in
Jun. 2016; 1 ind. in Sep. 2016, 1 ind. from Mar.-Sep. 2017).
6.5.11 About
the body size, larger individuals of Carcinoscorpius
rotundicauda were usually found in ST and TC1 relative to those in TC3 from Sep. 2012 to Jun. 2017. But
the body size was higher in TC3 and ST followed by TC1 from Sep. 2017 to Mar.
2018. For Tachypleus
tridentatus, larger individuals were usually found
in ST followed by TC3 and TC1 throughout the montioring period.
6.5.12 In general, it was obvious that TC3 and ST
(western shore of Tung Chung Wan) was an important nursery ground for horseshoe
crab especially newly hatched individuals due to larger area of suitable
substratum (fine sand or soft mud) and less human disturbance (far from urban
district). Relatively, other sampling zones were not a suitable nursery ground
especially TC2. Possible factors were less area of suitable substratum
(especially TC1) and higher human disturbance (TC1 and TC2: close to urban
district and easily accessible). In TC2, large daily salinity fluctuation was a
possible factor either since it was flushed by two rivers under tidal
inundation. The individuals inhabiting TC1 and TC2 were confined in small
foraging area due to limited area of suitable substrata. Although a mating pair
of Carcinoscorpius rotundicauda was once found in TC2, the hatching rate and survival rate of newly hatched
individuals were believed very low.
Seasonal
variation of horseshoe crab population
6.5.13
Throughout the monitoring period, the search
record of horseshoe crab declined obviously during dry season especially
December (Figures 3.3 and 3.4 of
Appendix I). In Dec. 2012, 4 individuals of Carcinoscorpius rotundicauda and 12 individuals of Tachypleus tridentatus were found only. In Dec. 2013,
no individual of horseshoe crab was found. In Dec. 2014, 2 individuals of Carcinoscorpius rotundicauda and 8 individuals of Tachypleus tridentatus were found only. In Dec. 2015, 2
individuals of Carcinoscorpius rotundicauda, 6 individuals of Tachypleus tridentatus and one newly hatched,
unidentified individual were found only. The horseshoe crabs were inactive and burrowed in the sediments during
cold weather (<15 ºC). Similar results of low search record in dry season were reported in a
previous territory-wide survey of horseshoe crab. For example, the search
records in Tung Chung Wan were 0.17 ind. hr-1
person-1 and 0.00 ind. hr-1 person-1 in wet season and dry season respectively (details see Li, 2008).
Relatively the serach records were much higher in Dec. 2016. There were totally 70
individuals of Carcinoscorpius rotundicauda and 24 individuals of Tachypleus tridentatus in TC3 and ST. Because the survey was arranged in early December
while the weather was warm with sunlight (~22 ˘XC during dawn according to Hong
Kong Observatory database, Chek Lap Kok station on 5 Dec). In contrast, there was no search record in TC1 and TC2 because the
survey was conducted in mid December with colder and cloudy weather (~20 ˘XC during dawn on 19 Dec). The horseshoe crab activity would decrease gradually with the colder climate. In Dec.
2017 (present survey), the weather was cold (13-15 ºC during
dawn) that very few
individuals of both specis could be found as mentioned above.
6.5.14
From Sep. 2012 to Dec. 2013, Carcinoscorpius rotundicauda was a less
common species relative to Tachypleus
tridentatus. Only 4 individuals were ever recorded in ST in Dec. 2012. This
species had ever been believed of very low density in ST hence the encounter
rate was very low. Since Mar. 2014, it was found in all sampling zones with
higher abundance in ST. Based on its average size (mean prosomal width 39.28-49.81
mm), it indicated that breeding and spawning of this species had occurred about
3 years ago along the coastline of Tung Chun Wan. However, these individuals
were still small while their walking trails were inconspicuous. Hence there was
no search record in previous sampling months. Since Mar. 2014, more individuals
were recorded due to larger size and higher activity (i.e. more conspicuous
walking trail).
6.5.15 For Tachypleus tridentatus, sharp
increase of number of individuals was recorded in ST during the wet season of
2013 (from Mar. to Sep.). According to a personal conversation with Prof. Shin
(CityU), his monitoring team had recorded similar increase of horseshoe crab
population during wet season. It was believed that the suitable ambient
temperature increased its conspicuousness. However similar pattern was not
recorded in the following wet seasons. The number of individuals increased in
Mar. and Jun. 2014 followed by a rapid decline in Sep. 2014. Then the number of
individuals fluctuated slightly in TC3 and ST until Mar. 2017. Apart from
natural mortality, migration from nursery soft shore to subtidal habitat was
another possible cause. Since the mean prosomal width of Tachypleus tridentatus
continued to grow and reached about 50 mm since Mar. 2014. Then it varied
slightly between 35-65 mm from Sep. 2014 to Mar. 2017. Most of the individuals
might have reached a suitable size (e.g. prosomal width 50-60 mm) strong enough
to forage in sub-tidal habitat. In Jun. 2017, the number of individuals
increased sharply again in TC3 and ST. Although mating pair of Tachypleus
tridentatus was not found in previous surveys, there should be new round of
spawning in the wet season of 2016. The individuals might have grown to a more
conspicuous size in 2017 accounting for higher search record. In Sep. 2017 and Mar. 2018
(present survey), moderate numbers of individual were found in TC3 and ST
indicating a stable population size.
6.5.16
Recently, Carcinoscorpius
rotundicauda was a more common horseshoe crab species in Tung Chung Wan. It
was recorded in the four sampling zones while the majority of population
located in TC3 and ST. Due to potential breeding last year, Tachypleus tridentatus became common
again and distributed in TC3 and ST only. Since TC3 and ST were regarded as
important nursery ground for both horseshoe crab species, box plots of prosomal
width of two horseshoe crab species were constructed to investigate the changes
of population in details.
Box plot of horseshoe crab populations in TC3
6.5.17
Figure 3.6 of Appendix I shows the changes of prosomal width of Carcinoscorpius
rotundicauda and Tachypleus tridentatus in TC3. As mentioned above, Carcinoscorpius
rotundicauda was rarely found between Sep. 2012 and Dec. 2013 hence the data were
lacking. In Mar 2014, the major size (50% of individual records between upper (top of red box) and lower
quartile (bottom of blue box)) ranged 40-60 mm while only few individuals were
found. From Mar. 2014 to Jun. 2017, the median prosomal width (middle line of
whole box) and major size (whole box) decreased after Mar. of every year. It
was due to more small individuals found. It indicated new rounds of spawning.
Also there were slight increasing trends of body size from Jun. to Mar. of next
year since 2015. It indicated a stable growth of individuals. Focused on larger
juveniles (upper whisker), the size range was quite variable (prosmal width
60-90 mm) along the sampling months. Juveniles reaching this size might gradually
migrate to sub-tidal habitats.
6.5.18 For Tachypleus
tridentatus, the major size ranged 20-50 mm while the number of individuals
fluctuated from Sep. 2012 to Jun. 2014. Then a slight but consistent growing
trend was observed from Sep. 2014 to Jun. 2015. The prosomal width increased
from 25-35 mm to 35-65 mm. As mentioned, the large individuals might have reached a
suitable size for migrating from the nursery soft shore to subtidal habitat. It
accounted for the declined population in TC3. From Mar. to Sep. 2016, slight
increasing trend of major size was noticed again. From Dec. 2016 to Jun. 2017, similar
increasing trend of major size was noted with much higher number of
individuals. It reflected new round of spawning. In Sep. 2017, the major size
decreased while the trend was different from previous two years. Such decline
might be the cause of serial cyclone hit between Jun. and Sep. 2017 (to be
discussed in the 'Seagrass survey' section). From Dec. 2017 to Mar. 2018
(present survey), slight increasing trend was noted again. Across the whole monitoring period, the larger juveniles (upper whisker)
usually reached 60-80 mm in prosomal width, even 90 mm occasionally. Juveniles
reaching this size might gradually migrate to sub-tidal habitats.
Box plot of horseshoe crab populations in ST
6.5.19
Figure 3.7 of Appendix I shows the changes of prosomal width of Carcinoscorpius
rotundicauda and Tachypleus tridentatus in ST. As mentioned above, Carcinoscorpius
rotundicauda was rarely found between Sep. 2012 and Dec. 2013 hence the
data were lacking. From Mar. 2014 to Sep. 2017, the size of major population
decreased and more small individuals (i.e. lower whisker) were recorded after
Jun. of every year. It indicated new round of spawning. Also there were similar
increasing trends of body size from Sep. to Jun. of next year between 2014 and
2017. It indicated a stable growth of individuals. Across the whole monitoring
period, the larger juveniles (i.e. upper whisker) usually ranged 60-80 mm in
prosomal width except one individual (prosomal width 107.04 mm) found in Mar.
2017. It reflected juveniles reaching this size would gradually migrate to
sub-tidal habitats.
6.5.20
For Tachypleus tridentatus, a
consistent growing trend was observed for the major population from Dec. 2012
to Dec. 2014 regardless of change of search record. The prosomal width increased from 15-30 mm to 60-70 mm. As mentioned,
the large juveniles might have reached a suitable size for migrating from the nursery soft
shore to subtidal habitat. From Mar. to Sep. 2015, the size of major population
decreased slightly to a prosomal width 40-60 mm. At the same time, the number
of individuals decreased gradually. It further indicated some of large
juveniles might have migrated to sub-tidal habitat, leaving the smaller
individuals on shore. There was an overall growth trend. In Dec. 2015, two big
individuals (prosomal width 89.27 mm and 98.89 mm) were recorded only while it
could not represent the major population. In Mar. 2016, the number of
individual was very few in ST that no boxplot could be produced. In Jun. 2016,
the prosomal width of major population ranged 50-70 mm. But it dropped clearly
to 30-40 mm in Sep. 2016 followed by an increase to 40-50 mm in Dec. 2016,
40-70 mm in Mar. 2017 and 50-60mm in Jun. 2017. Based on overall higher number
of small individuals from Jun. 2016 to Sep. 2017, it indicated new round of
spawning. From Sep. 2017 to Mar. 2018 (present survey), the major size range
increased slightly from 40-50 mm to 45-60 mm indicating a continous growth. Throughout
the monitoring period, the larger junveniles ranged 60-80 mm in prosomal width.
Juveniles reaching this size would gradually migrate to sub-tidal habitats.
6.5.21 As a summary for horseshoe crab
populations in TC3 and ST, there were spawning of Carcinoscorpius rotundicauda from 2014 to 2016 while the spawning
time should be in spring. There were consistent, increasing trends of population size in these two
sampling zones. For Tachypleus tridentatus, small
individuals were rarely found in both zones from
2014 to 2015. It was believed no occurrence of successful spawning. The
existing individuals (that recorded since 2012) grew to a mature size and
migrated to sub-tidal habitat. Hence the number of individuals decreased
gradually. In 2016, new round of spawning was recorded in ST while increasing
number of individuals and body size was noticed.
Impact of the HKLR project
Seagrass Beds
6.5.23 From Sep. to Mar. 2018 (present
survey), no seagrass bed was recorded in Tung Chung
Wan. Extensive area of mudflat, where used to be covered by seagrass beds,
re-exposed along TC3 and ST (Figure 3.8
of Appendix
I). In the
previous survey of Jun. 2017, two species of seagrass Halophila ovalis and Zostera
japonica were recorded in TC3 and ST (Figure
3.9 of Appendix I). There was still extensive seagrass area (~17046.5 m2)
of Halophila ovalis along the mudflat
between TC3 and ST at 0.5-2.0 m above C.D.. Another seagrass species Zostera japonica, which was much lower
in vegetation area (~105.4 m2), was co-existing with few patches of Halophila ovalis nearby the mangrove
strand. The disappearance of seagrass beds would be discussed in later
paragraphs.
6.5.24 According to the previous results, majority of seagrass bed was confined
in ST, the temporal change of both seagrass species were investigated in details:
Temporal
variation of seagrass beds
6.5.25 Figure
3.10 of Appendix
I shows the changes of estimated total area of
seagrass beds in ST along the sampling months. For Zostera japonica, it
was not recorded in the 1st and 2nd surveys of monitoring
programme. Seasonal recruitment of few small patches (total seagrass area: 10 m2) was found in
Mar. 2013 that grew within the large patch of seagrass Halophila ovalis. Then the patch size increased and merged gradually with the warmer
climate from Mar. to Jun. 2013 (15 m2). However the patch size
decreased and remained similar from Sep. 2013 (4 m2) to Mar. 2014 (3
m2). In Jun. 2014, the patch size increased obviously again (41 m2)
with warmer climate followed by a decrease between Sep. 2014 (2 m2)
and Dec. 2014 (5 m2). From Mar. to Jun. 2015, the patch size
increased sharply again (90 m2). It might be due to the
disappearance of the originally dominant seagrass Halophila ovalis resulting in less competition
for substratum and nutrients. From Sep.2015 to Jun.2016, it was found
coexisting with seagrass Halophila ovalis with steady increasing patch
size (from 44 m2
to 115 m2) and variable coverage. In Sep. 2016, the patch size
decreased again to (38 m2) followed by an increase to a horizontal strand (105.4 m2) in Jun. 2017 (present
survey). And it was no longer co-existing with Halophila ovalis. Between Sep. 2014 and Jun.
2017, an increasing trend was noticed from Sep. to Jun. of next year followed
by a rapid decline in Sep. of next year. It was possibly the causes of heat
stress, typhoon and stronger grazing pressure during wet season. In Sep. to
Mar. 2018 (present survey), no seagrass patch of Zostera japonica was found.
6.5.26 For Halophila ovalis, it was recorded
as 3-4 medium to large patches (area 18.9-251.7 m2; vegetation coverage
50-80%) beside the mangrove vegetation at tidal level 2 m above C.D. in Sep.
2012 (first survey). The
total seagrass bed area grew steadily from 332.3 m2 in Sep. 2012 to
727.4 m2 in Dec. 2013. Flowers were observed in the largest patch
during its flowering period. In Mar. 2014, 31 small to medium patches were newly recorded
(variable area 1-72 m2 per patch, vegetation coverage 40-80% per
patch) in lower tidal zone between 1.0 and 1.5 m above C.D. The total seagrass
area increased further to 1350 m2. In Jun. 2014, these small and
medium patches grew and extended to each other. These patches were no longer
distinguishable and were covering a significant mudflat area of ST. It was
generally grouped into 4 large patches (1116 ˇV 2443 m2) of seagrass
beds characterized of patchy distribution, variable vegetable coverage (40-80%)
and smaller leaves. The total seagrass bed area increased sharply to 7629 m2.
In Sep. 2014, the total seagrass area declined sharply to 1111 m2.
There were only 3-4 small to large patches (6-253 m2) at high tidal
level and 1 large patch at low tidal level (786 m2). Typhoon or strong water current was a possible cause (Fong, 1998). In Sep. 2014,
there were two tropical cyclone records in Hong Kong (7th-8th
Sep.: no cyclone name, maximum signal number 1; 14th-17th
Sep.: Kalmaegi, maximum signal number 8SE) before the seagrass survey dated 21st
Sep. 2014. The strong water current caused by the cyclone, Kalmaegi especially,
might have given damage to the seagrass beds. In addition, natural heat stress
and grazing force were other possible causes reducing seagrass beds area.
Besides, very small patches of Halophila ovalis could be found in other mud flat area in addition to the recorded
patches. But it was hardly distinguished due to very low coverage (10-20%) and
small leaves.
6.5.27 In
Dec. 2014, all the seagrass patches of Halophila
ovalis disappeared in ST. Figure
3.10 of Appendix
I shows the
difference of the original seagrass beds area nearby the mangrove vegetation at
high tidal level between Jun. 2014 and Dec. 2014. Such rapid loss would not be seasonal phenomenon because the seagrass
beds at higher tidal level (2.0 m above C.D.) were present and normal in
December 2012 and 2013. According to Fong (1998), similar incident had occurred
in ST in the past. The original seagrass area had declined significantly during
the commencement of the construction and reclamation works for the
international airport at Chek Lap Kok in 1992. The seagrass almost disappeared
in 1995 and recovered gradually after the completion of reclamation works.
Moreover, incident of rapid loss of seagrass area was also recorded in another
intertidal mudflat in Lai Chi Wo in 1998 with unknown reason. Hence Halophila ovalis was regarded as a short-lived
and r-strategy seagrass that could
colonize areas in short period but disappears quickly under unfavourable
conditions (Fong, 1998).
Unfavourable conditions to seagrass Halophila
ovalis
6.5.28 Typhoon or strong water current was suggested as one unfavourable
condition to Halophila ovalis (Fong,
1998). As mentioned above, there were two tropical cyclone records in Hong Kong
in Sep. 2014. The strong water current caused by the cyclones might have given
damage to the seagrass beds.
6.5.29
Prolonged
light deprivation due to turbid water would be another unfavouable condition.
Previous studies reported that Halophila ovalis had little tolerance to
light deprivation. During experimental darkness, seagrass biomass declined
rapidly after 3-6 days and seagrass died completely after 30 days. The rapid
death might be due to shortage of available carbohydrate under limited
photosynthesis or accumulation of phytotoxic end products of anaerobic
respiration (details see Longstaff et al., 1999). Hence the seagrass bed
of this species was susceptible to temporary light deprivation events such as
flooding river runoff (Longstaff and Dennison, 1999).
6.5.30
In order to investigate any deterioration of
water quality (e.g. more turbid) in ST, the water quality measurement results
at two closest monitoring stations SR3 and IS5 of the EM&A programme were
obtained from the water quality monitoring team. Based on the results from June
to December 2014, the overall water quality was in normal fluctuation except
there was one exceedance of suspended solids (SS) at both stations in
September. On 10th Sep., 2014, the SS concentrations measured during
mid-ebb tide at stations SR3 (27.5 mg/L) and IS5 (34.5 mg/L) exceeded the
Action Level (≤23.5 mg/L and 120% of upstream control stationˇ¦s reading) and
Limit Level (≤34.4 mg/L and 130% of upstream control stationˇ¦s reading)
respectively. The turbidity readings at SR3 and IS5 reached 24.8-25.3 NTU and
22.3-22.5 NTU respectively. The temporary turbid water should not be caused by
the runoff from upstream rivers. Because there was no rain or slight rain from
1st to 10th Sep. 2014 (daily total rainfall at the Hong
Kong International Airport: 0-2.1 mm; extracted from the climatological data of
Hong Kong Observatory). The effect of upstream runoff on water quality should
be neglectable in that period. Moreover the exceedance of water quality was
considered unlikely to be related to the contract works of HKLR according to
the ˇĄNotifications of Environmental Quality Limits Exceedancesˇ¦ provided by the
respective environmental team. The respective construction of seawall and stone
column works, which possibly caused turbid water, were carried out within silt
curtain as recommended in the EIA report. Moreover there was no leakage of
turbid water, abnormity or malpractice recorded during water sampling. In
general, the exceedance of suspended solids concentration was considered to be
attributed to other external factors, rather than the contract works.
6.5.31
Based on the weather condition and water
quality results in ST, the co-occurrence of cyclone hit and turbid waters in Sep. 2014 might
have combined the adverse effects on Halophila ovalis that leaded to disappearance of
this short-lived and r-strategy
seagrass species. Fortunately Halophila
ovalis was a fast-growing
species (Vermaat et al., 1995). Previous studies showed that the
seagrass bed could be recovered to the original sizes in 2 months through
vegetative propagation after experimental clearance (Supanwanid, 1996).
Moreover it was reported to recover rapidly in less than 20 days after dugong
herbivory (Nakaoka and Aioi, 1999). As mentioned, the disappeared seagrass in
ST in 1995 could recover gradually after the completion of reclamation works
for international airport (Fong, 1998). The seagrass beds of Halophila ovalis might recolonize the mudflat of ST through seed reproduction as long
as there was no unfavourable condition in the coming months.
Recolonization of seagrass beds
6.5.32
Figure 3.10 of Appendix I shows the recolonization of
seagrass bed area in ST from Dec. 2014 to Jun. 2017. From Mar. to Jun. 2015, 2-3 small
patches of Halophila
ovalis were newly found coinhabiting with another
seagrass species Zostera japonica. But
its total patch area was still very low relative to the previous records. The
recolonization rate was low while cold weather and insufficient sunlight were
possible factors between Dec. 2014 and Mar. 2015. Moreover, it would need to
compete with seagrass Zostera japonica
for substratum and nutrient. Since Zostera japonica had extended and had covered the original seagrass bed of Halophila ovalis at certain degree. From Jun.
2015 to Mar. 2016, the total seagrass area of Halophila ovalis had increased rapidly
from 6.8 m2 to 230.63 m2. It had recolonized its
original patch locations and covered Zostera
japonica. In Jun. 2016, the total seagrass area increased sharply to 4707.3 m2. Similar to the previous records of Mar to Jun. 2014, the original
patch area increased further to a horizontally long strand. Another large
seagrass beds colonized the lower
tidal zone (1.0-1.5 m above C.D.). In Sep. 2016, this patch extended much and
covered significant soft mud area of ST, resulting in sharp increase of total
area (24245 m2). It indicated the second extensive colonization of
this r-strategy seagrass. In
Dec. 2016, this extensive seagrass patch decreased in size and had separated into few,
undistinguishable patches. Moreover, the horizontal strand nearby the mangrove
vegetation decreased in size (Fig. 3.10). The total seagrass bed decreased to
12550 m2. From Mar. to Jun. 2017, the seagrass bed area remained
generally stable (12438-17046.5 m2) but the vegetation coverage
fluctuated (20-50% in Mar. 2017 to 80-100% in Jun. 2017).
Re-disappearance of seagrass bed
6.5.33
In Sep 2017, the whole seagrass
bed of Halophila ovalis disappeared
again along the shore of TC3 and ST (Figure
3.11 of Appendix I). It was similar to the case between Sep. and Dec. 2014.
As mentioned, strong water current (e.g. cyclone) or deteriorated water quality
(e.g. high turbidity) were the possible causes.
6.5.34
Between the survey periods of
Jun. and Sep. 2017, there were four tropical cyclone records in Hong Kong
(Merbok in 12-13th, Jun.; Roke in 23rd, Jul.; Hato in
22-23rd, Aug.; Pakhar in 26-27th, Aug.) (online database
of Hong Kong Observatory). All of them reaches signal 8 or above especially
Hato (highest signal 10).
6.5.35
According to the water quality
monitoring results (Jul. to Aug. 2017) of the two closest monitoring stations
SR3 and I5 of the respective EM&A programme, the overall water quality was
in normal fluctuation. There was one exceedance of suspended solids (SS) at SR3
on 12 Jul. 2017. The SS concentration reached 24.7 mg/L during mid-ebb tide. It
exceeded the Action Level (≤23.5 mg/L) but was far below the Limit Level (≤34.4 mg/L). Since such exceedance was slight
and temporary, its effect to seagrass bed should be minimal.
6.5.36
Overall, the disappearance of
seagrass beds in ST was believed the cause of serial cyclone hit in Jul and
Aug. 2017. Based on previous findings, the seagrass beds of both species were
expected to recolonize the mudflat as long as the vicinal water quality was
normal. The whole recolonization process (from few, small patches to extensive
strand) would be gradual lasting 1.5 to 2 years. From Dec. 2017 to Mar. 2018,
there was still no recolonization of few, small patches of seagrass at the
usual location. It was different from previous re-colonization (Mar. 2015 -
Jun. 2017) that new, small seagrass patches were found within three months. The
results of coming wet season survey (Jun. 2018) would provide a better
understanding about seagrass status.
Impact of the HKLR
project
Intertidal Soft Shore Communities
6.5.38 Table 3.2 and Figure 3.12 of Appendix I show the types of substratum along the
horizontal transect at every tidal level in all sampling zones. The relative
distribution of different substrata was estimated by categorizing the
substratum types (Gravels & Boulders / Sands / Soft mud) of the ten random
quadrats along the horizontal transect. The distribution of substratum types
varied among tidal levels and sampling zones:
ˇP
In TC1, high percentages of ˇĄGravels and
Bouldersˇ¦ (80%) were recorded at high and mid tidal levels. Even distribution
of ˇĄSoft mudˇ¦ (50%) and ˇĄGravels and Bouldersˇ¦ (40%) was recorded at low tidal
level.
ˇP
In TC2, higher percentages of 'Sands' (50%)
and 'Soft mud' (30%) were recorded at high tidal level. There were higher
percentages of 'Sands' (50%) and 'Gravels and Boulders' (40%) at mid tidal
level. At low tidal level, the major substratum type was 'Soft mud' (80%).
ˇP
In TC3, high percentages of ˇĄSandsˇ¦ (90-100%)
were recorded at high and mid tidal levels. At low tidal level, the major
substratum type was ˇĄGravels and Bouldersˇ¦ (90%).
ˇP
In ST, ˇĄGravels and Bouldersˇ¦ was the main
substratum (100%) at high tidal level. At mid tidal level, there was high
percenage of ˇĄGravels and Bouldersˇ¦ (70%) followed by 'Soft mud' (30%). At low
tidal level, the substartum types were mainly ˇĄSoft mudˇ¦ (70%) and 'Sands'
(30%).
6.5.39 There was neither consistent
vertical nor horizontal zonation pattern of substratum type in all sampling zones.
Such heterogeneous variation should be caused by different hydrology (e.g. wave
in different direction and intensity) received by the four sampling zones.
6.5.40 Table 3.3 of Appendix I lists the total abundance, density and
number of taxon of every phylum in this survey. A total
of 14079 individuals were recorded. Mollusca was clearly the
most abundant phylum (total abundance 13536 ind., density 451 ind. m-2, relative abundance 96.1 %). The second and third abundant phya were Arthropoda (421 ind., 14 ind. m-2, 3.0 %) and Annelida (57 ind., 2 ind. m-2, 0.4 %) respectively. Relatively other phyla were very low in abundances (density £1 ind. m-2, relative abundance £0.2 %). Moreover, the most diverse phylum was Mollusca (37 taxa)
followed by Arthropoda (16 taxa)
and Annelida (9 taxa). There was 1-3 taxa recorded only for other phyla. The taxonomic resolution and complete list of recorded fauna are shown
in Annexes IV and V of Appendix I respectively.
6.5.41 Table 3.4 of Appendix I shows the number of individual, relative abundance and density of each
phylum in every sampling zone. The total abundance (2198-5497 ind.) varied
among the four sampling zones while the phyla distributions were similar. In general, Mollusca was the
most dominant phylum (no. of individuals: 2030-5395
ind.; relative abundance 92.4-98.1 %; density 271-719 ind. m-2). Other phyla were much lower in number of individuals. Arthropoda (55-144
ind.; 1.4-6.2 %; 7-19 ind. m-2) was the second abundant phylum. Annelida (9-25 ind.; 0.4-0.8 %; 1-3 ind. m-2) was the third abundant phylum in TC2, TC3 and ST. Sipuncula (7 ind.; 0.1 %; 1 ind. m-2) was the third
abundant phylum in TC1 while it was also commonly found in TC2 and TC3 (8-12
ind.; 0.2-0.5 %; 1-2 ind. m-2). Relatively
other phyla were very low in abundance in all sampling zones.
Dominant species in every sampling zone
6.5.42
Table 3.5 of Appendix I lists
the abundant species (relative abundance >10 %) in every sampling
zone. In the present survey, most of the listed abundant species were of low
to moderate densities (50-250 ind. m-2). Few listed species of high
or very high density (> 250 ind. m-2) were regarded as dominant
species. Other listed species of lower density (< 50 ind. m-2)
were regared as common species.
6.5.43
In TC1, the substratum was mainly ˇĄGravels
and Bouldersˇ¦ at high tidal level. It was dominanted by gastropod Batillaria multiformis (644 ind. m-2, relative abundance 64 %) at very high density
followed by gastropod Cerithidea djadjariensis (207 ind. m-2,
20 %). At mid tidal level (substratum type ˇĄGravels
and Bouldersˇ¦), there were few abundant gastropods Batillaria
multiformis (180
ind. m-2, 30 %), Cerithidea djadjariensis (117 ind. m-2,
20 %) and Monodonta labio (86 ind. m-2, 14 %) at
low-moderate densities. And the rock oyster Saccostrea cucullata (118
ind. m-2, 20 %, attached on boulders) was also abundant. At low
tidal level (substratum types 'Soft mud' and ˇĄGravels
and Bouldersˇ¦), rock
oyster Saccostrea cucullata (212 ind. m-2, 36 %) was clearly
abundant, attaching on the boulders. There were also gastropods Monodonta
labio (78 ind. m-2, 13 %), Cerithidea djadjariensis (64 ind. m-2,
11 %) and Batillaria multiformis (56 ind. m-2, 10 %).
6.5.44
In TC2, the
substratum was either 'Sands' and 'Soft mud' at high
tidal level. Gastropod Cerithidea djadjariensis (141 ind. m-2, 44 %)
was abundant at moderate density. Other common fauna included gastropods Batillaria
zonalis (46 ind. m-2, 14 %), Batillaria
multiformis (36 ind. m-2, 11 %) and rock oyster Saccostrea
cucullata (40 ind. m-2, 13 %, attached on boulders). At mid
tidal level (main substratum types 'Sands' and 'Soft mud'), there was abundant
rock oyster Saccostrea cucullata at modeate density (106 ind. m-2,
36 %) followed by common gastropods Batillaria zonalis (57 ind. m-2, 19 %) and Monodonta
labio (34 ind. m-2, 12 %). At low tidal level whose substratum type
was mainly soft mud, rock oyster Saccostrea cucullata was also abudnant (151
ind. m-2, 41 %) followed by common gastropod Batillaria zonalis (64 ind. m-2, 18 %) and
barnacle Balanus amphitrite (38 ind. m-2, 10 %,
attached on boulders.
6.5.45
In TC3, the major substratum types were mainly ˇĄSandsˇ¦ at high and mid tidal
levels. Gastropods Batillaria multiformis (252 ind. m-2, 47 %) and Cerithidea
djadjariensis (204
ind. m-2, 38 %) were both abundant species at high tidal level. At
mid tidal level, gastropod Cerithidea djadjariensis (180 ind. m-2,
47 %) was found abundant followed by other grastropods Batillaria
multiformis (88 ind. m-2, 23 %), Batillaria zonalis (48
ind. m-2, 13 %) and Cerithidea cingulata (39 ind. m-2,
10 %). At low tidal level (major
substratum: ˇĄGravels and Bouldersˇ¦), rock oyster Saccostrea cucullata (268 ind. m-2, 40 %) and gastropod
Monodonta labio (202 ind. m-2, 30 %) were
abundant at moderate densities.
6.5.46
In ST, the major substratum types were mainly ˇĄGravels
and Bouldersˇ¦ at high and mid tidal levels. Gastropod Batillaria multiformis
(109 ind. m-2, 27 %),
Monodonta labio (84 ind. m-2, 21 %) and rock oyster Saccostrea
cucullata (60 ind. m-2, 15 %, attached on boulders) were
abundant at low-moderate densities followed by common gastropod Batillaria bornii
(45 ind. m-2, 11 %). At mid tidal level, rock oyster Saccostrea
cucullata (110 ind. m-2, 33%) was abundant at moderate density followed by
common gastropods Monodonta labio (40 ind. m-2, 12 %) and Lunella coronata (34 ind. m-2, 10 %). At low tidal level (major substratum
type: ˇĄSoft mudˇ¦), there were two common speices including rock oyster Saccostrea
cucullata (43 ind. m-2, 31%) and barnacle Balanus amphitrite (29 ind. m-2, 21 %).
6.5.47 In general, there was no consistent zonation pattern of
species distribution across all sampling zones and tidal levels. The
species distribution should be determined by the type of substratum primarily.
In general, gastropods Batillaria multiformis (total
number of individuals: 3608 ind., relative abundance 25.6 %), Cerithidea djadjariensis (2498
ind., 17.7 %), Batillaria zonalis (713 ind.,
5.1 %) and Cerithidea
cingulata (580 ind., 4.1 %) were the most commonly occurring
species on sandy and soft mud substrata. Rock oyster Saccostrea cucullata (2840 ind.,
20.2 %), gastropods Monodonta labio (1437 ind., 10.2 %) and Lunella coronata
(400 ind.,
2.8 %) were commonly occurring species inhabiting
gravel and boulders substratum.
Biodiversity and abundance of soft shore communities
6.5.48 Table 3.6 of Appendix I shows the mean values of species number,
density, biodiversity index Hˇ¦ and species evenness J of soft shore communities at every tidal level and in every sampling zone. As mentioned above, the
differences among sampling zones and tidal levels were determined by the major type of substratum primarily.
6.5.49 Among the sampling zones, there was no obvious difference of mean
species number, H' and J regardless of tidal levels. The mean species
numbers ranged 9-12 spp. 0.25 m-2 among all sampling zones. The mean
density of TC1 (733 ind. m-2) were higher than TC3 (527 ind. m-2)
followed by TC2 and ST (293-325 ind. m-2). The much higher density
of TC1 was mainly accounted by one gastropod species of
high abundance at high tidal level. It leaded to moderate species evenness. ST
was lowest in mean density while the taxa distribution was even. It also leaded
to moderate species evenness. Overall the mean Hˇ¦ and J were similar,
that ranged 1.3-1.7 and 0.6-0.7 respectively among all sampling zones.
6.5.50 Across the tidal levels, there were slightly increasing trends of
mean species number and H' from high
to low tidal level in TC1, TC2 and TC3 but vice versa in ST. For the mean
density, there were generally decreasing trends in TC1 and ST from high to low
tidal level. But there was no consistent difference of J observed across the tidal levels. In general, the spatial
differences of these biological parameters were highly related to substratum
types.
6.5.51 Figures 3.13 to 3.16 of
Appendix I show the temporal changes of mean species number, mean density,
Hˇ¦ and J at every
tidal level and in every sampling zone along the sampling months. In
general, all the biological parameters fluctuated seasonally throughout the
monitoring period. Lower mean species number and density were recorded in dry
season (Dec.) but the mean H' and J fluctuated within a stable range.
6.5.52 From Jun. to Dec. 2017, there
were steady decreasing trends of mean species number and density in TC2, TC3
and ST regardless of tidal levels. It might be an unfavourable change
reflecting environmental stresses. The heat stress and serial cyclone hit were
believed the causes during the wet season of 2017. It was expected that the
intertidal community would recover gradually in the following wet season. In
Mar. 2018 (present survey), increases of mean species number and density were
observed in all sampling zones. It indicated the recovery of intertidal
community.
Impact
of the HKLR project
6.6.1 Chan,
K.K., Caley, K.J., 2003. Sandy Shores, Hong Kong Field Guides 4. The Department
of Ecology & Biodiversity, The University of Hong Kong. pp 117.
6.6.2 Dai,
A.Y., Yang, S.L., 1991. Crabs of the China Seas. China Ocean Press. Beijing.
6.6.3 Dong,
Y.M., 1991. Fauna of ZheJiang Crustacea. Zhejiang Science and Technology
Publishing House. ZheJiang.
6.6.4 EPD,
1997. Technical Memorandum on Environmental Impact Assessment Process (1st
edition). Environmental Protection Department, HKSAR Government.
6.6.5 Fauchald,
K., 1977. The polychaete worms. Definitions and keys to the orders, families
and genera. Natural History Museum of Los Angeles County, Science Series 28.
Los Angeles, U.S.A..
6.6.6 Fong,
C.W., 1998. Distribution of Hong Kong seagrasses. In: Porcupine! No. 18. The
School of Biological Sciences, The University of Hong Kong, in collaboration
with Kadoorie Farm & Botanic Garden Fauna Conservation Department, p10-12.
6.6.7 Li,
H.Y., 2008. The Conservation of Horseshoe Crabs in Hong Kong. MPhil Thesis,
City University of Hong Kong, pp 277.
6.6.8 Longstaff,
B.J., Dennison, W.C., 1999. Seagrass survival during pulsed turbidity events:
the effects of light deprivation on the seagrasses Halodule pinifolia and Halophila ovalis. Aquatic Botany 65
(1-4), 105-121.
6.6.9 Longstaff,
B.J., Loneragan, N.R., Oˇ¦Donohue, M.J., Dennison, W.C., 1999. Effects of light
deprivation on the survival and recovery of the seagrass Halophila ovalis (R. Br.) Hook. Journal of Experimental Marine Biology
and Ecology 234 (1), 1-27.
6.6.10 Nakaoka,
M., Aioi, K., 1999. Growth of seagrass Halophila
ovalis at dugong trails compared to existing within-patch variation in a
Thailand intertidal flat. Marine Ecology Progress Series 184, 97-103.
6.6.11 Pielou,
E.C., 1966. Shannonˇ¦s formula as a measure of species diversity: its use and
misuse. American Naturalist 100, 463-465.
6.6.12 Qi,
Z.Y., 2004. Seashells of China. China Ocean Press. Beijing, China.
6.6.13 Qin,
H., Chiu, H., Morton, B., 1998. Nursery beaches for Horseshoe Crabs in Hong
Kong. In: Porcupine! No. 18. The School of Biological Sciences, The University
of Hong Kong, in collaboration with Kadoorie Farm & Botanic Garden Fauna
Conservation Department, p9-10.
6.6.14 Shannon,
C.E., Weaver, W., 1963. The Mathematical Theory of Communication. Urbana:
University of Illinois Press, USA.
6.6.15 Shin,
P.K.S., Li, H.Y., Cheung, S.G., 2009. Horseshoe Crabs in Hong Kong: Current
Population Status and Human Exploitation. Biology and Conservation of Horseshoe
Crabs (part 2), 347-360.
6.6.16 Supanwanid,
C., 1996. Recovery of the seagrass Halophila
ovalis after grazing by dugong. In: Kuo, J., Philips, R.C., Walker, D.I.,
Kirkman, H. (eds), Seagrass biology: Proc Int workshop, Rottenest Island,
Western Australia. Faculty of Science, The University of Western Australia,
Nedlands, 315-318.
6.6.17 Vermaat,
J.E., Agawin, N.S.R., Duarte, C.M., Fortes, M.D., Marba. N., Uri, J.S., 1995.
Meadow maintenance, growth and productivity of a mixed Philippine seagrass bed.
Marine Ecology Progress Series 124, 215-225.
6.6.18 Yang,
D.J, Sun, R.P., 1988. Polychaetous annelids commonly seen from the Chinese
waters (Chinese version). China Agriculture Press, China.
7
Environmental Site Inspection and Audit
7.1.1
Site Inspections were carried out on a weekly basis to monitor the
implementation of proper environmental pollution control and mitigation
measures for the Project. During the reporting month, five site inspections
were carried out on 1, 7, 14, 21 and 27 March 2018.
7.1.2 A summary of observations
found during the site inspections and the follow up actions taken by the Contractor are described in Table 7.1.
Table 7.1 Summary
of Environmental Site Inspections
Date of Audit
|
Observations
|
Actions Taken by Contractor / Recommendation
|
Date of Observations Closed
|
7 Feb 2018
|
1.
Site
runoff was not controlled properly to prevent discharge entering into marine
water at S7.
|
1. Proper bunding were set up to prevent
wastewater from site entering into marine water at S7.
|
1 Mar 2018
|
23 Feb 2018
|
1.
No
drip tray was provided for an oil drum at N30.
2.
No
drip tray was provided for oil drums at S16.
3.
No
drip tray was provided for chemical container at N30.
4.
Gap of
silt curtain was observed at Portion X.
|
1.
The
oil drum wad removed from N30.
2.
The
oil drums were removed from S16.
3.
The
chemical container was removed from N30.
4.
The
silt curtains were maintained properly at Portion X.
|
1 Mar 2018
|
1 Mar 2018
|
1.
Gaps
of silt curtain was observed at Portion X.
2.
Stagnant
water was observed inside a drip tray at S16.
3.
General
refuse was observed on the ground at S16.
4.
Construction
waste was accumulated on the ground at S15.
|
1. The silt curtains were maintained properly at Portion X.
2. The stagnant water was cleared inside the drip tray at S16.
3. The general refuse was removed on the ground from S16.
4.
The construction waste was
removed on the ground from S15.
|
7 Mar 2018
|
7 Mar 2018
|
1.
Gaps
of silt curtain was observed at Portion X.
2.
Chemical
containers were observed without drip trays at S7.
3.
Waste
was observed on the ground at S15.
4.
Wheel
washing facilities were observed insufficient at S25.
|
1.
The silt curtains were maintained
properly at Portion X.
2.
The chemical containers were
removed from S7.
3.
The waste was removed on the
ground from S15.
4. Wheel washing facilities with high pressure water jet was provided to
clean the vehicles before leaving the work area at S7.
|
14
Mar 2018
|
14 Mar 2018
|
1.
Waste
was accumulated at HAT.
2.
Waste
was observed on the ground at HAT.
3.
Waste
was accumulated at HMA
|
1.
The waste was removed from HAT.
2.
The waste was removed on the
ground from HAT.
3.
The waste was removed from HMA.
|
21 Mar 2018
|
21 Mar 2018
|
1.
Stagnant
water was observed inside a drip tray at HAT.
2.
Waste
was observed at HAT.
3.
Waste
was observed at N26.
4.
Dust
emission was observed during vehicle movement at N26.
|
1. The stagnant water was cleared inside the drip tray at HAT.
2. The waste was removed from HAT.
3. The waste was removed from N26.
4. Water spraying was applied on the haul road to prevent dust emission
at N26.
|
27 Mar 2018
|
27 Mar 2018
|
1.
Waste
was observed at HAT.
2.
Mechanical
cover of truck was not applied during transportation at S7.
3.
Oil
stain was observed at S7.
4.
Waste
was observed at S7.
5.
Gap of
the silt curtain was observed at Portion X.
|
The Contractor was recommended to:
1. remove the waste from HAT.
2. apply the mechanical
cover of the truck during transportation at S7.
3. remove the oil stain as
chemical waste at S7.
4. maintain the silt
curtains properly at Portion X.
|
Follow-up actions for the observations
issued for the last weekly site inspection of the
reporting month will be inspected during the next site inspection.
|
7.1.3 The Contractor has
rectified most of the observations as identified during environmental site
inspections within the reporting month. Follow-up actions for outstanding
observations will be inspected during the next site inspection.
7.2
Advice on the
Solid and Liquid Waste Management Status
7.2.1 The Contractor
registered as a chemical waste producer for the Project. Sufficient numbers of
receptacles were available for general refuse collection and sorting.
7.2.2
Monthly summary of waste flow table is detailed in Appendix J.
7.2.3 The Contractor was reminded that
chemical waste containers should be properly treated and stored temporarily in
designated chemical waste storage area on site in accordance with the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes.
7.3.1 The valid
environmental licenses and permits during the reporting month are summarized in
Appendix L.
7.4
Implementation Status of Environmental
Mitigation Measures
7.4.1 In response to the
site audit findings, the Contractors have rectified most of the observations as identified during environmental site
inspections during the reporting month. Follow-up actions for outstanding
observations will be inspected during the next site inspections.
7.4.2 A summary of the
Implementation Schedule of Environmental Mitigation Measures (EMIS) is
presented in Appendix M. Most of the
necessary mitigation measures were implemented properly.
7.4.3 Regular marine travel route for
marine vessels were implemented properly in accordance to the submitted plan
and relevant records were kept properly.
7.4.4 Dolphin Watching Plan was
implemented during the reporting month. No dolphins inside the silt curtain
were observed. The relevant records were kept properly.
7.5.1 For air quality, no Action and
Limit Level exceedances of 1-hr TSP were recorded at AMS5 and AMS6 during the
reporting month. No Action and Limit Level exceedances of 24-hr TSP were
recorded at AMS5 and AMS6 during the reporting month.
7.5.2 For construction noise, no Action
and Limit Level exceedances were recorded at the monitoring station during the
reporting month.
7.5.3 For marine water quality
monitoring, no Action Level and Limit Level exceedances of dissolved oxygen
level and turbidity level were recorded during the reporting month. No Limit
Level exceedances of suspended solids level were recorded during the reporting
month. Two Action Level exceedances of suspended solids level were recorded
during the reporting month. The exceedances of suspended solid level are
considered to be attributed to other external factors such as sea condition,
rather than the contract works. Therefore, the exceedances were considered as
non-contract related. Records of ˇ§Notification of Environmental Quality Limit
Exceedancesˇ¨ are provided in Appendix N.
7.6
Summary of Complaints,
Notification of Summons and Successful Prosecution
7.6.1
For Environmental Complaint No. COM-2017-129 in relation to the
environmental impacts (Cleanliness problem at East Coast Road) which was mentioned
in Monthly EM&A Report for December 2017. Complaint investigation was
undertaken. Based on the investigation result, there
is no direct evidence showing that that the complaint is related to Contract
No. HY/2011/03.
7.6.2
There was one complaint received in
relation to the environmental impacts for Monthly EM&A Report for February
2018. A follow-ups of complaint No. COM-2018-132 was received during reporting
period. Complaint Investigation is being undertaken. A summary of environmental
complaint for previous reporting month (February 2018) and during reporting
month is presented in Table 7.2.
Table
7.2 A
Summary of Environmental Complaint for Previous Reporting Month (February 2018)
and during the Reporting Month
Environmental Complaint No.
|
Date
of Complaint Received
|
Description
of Environmental Complaint
|
COM-2018-132
|
HyD (SOR referred the email from HyD to Contractor and ET on 13
February 2018) and EPD (ENPO referred the email from EPD to SOR, SOR sent
the email to Contractor and ET on 14 February 2018)
|
Complaint about Dust, Water Quality,
Construction Waste, Noise and Vibration for the Contract
|
Follow-ups of Complaint No COM-2018-132
|
HyD (SOR referred the
email from HyD to the Contractor and ET on 16 March) and EPD (ENPO referred
the email from EPD to SOR, who sent the email to the Contractor and ET on 21
March 2018)
|
Dust and Construction Waste
|
7.6.3
The details of cumulative statistics of Environmental Complaints
are provided in Appendix K.
7.6.4 No notification of summons and prosecution was received during the
reporting period. Statistics on notifications of summons and successful
prosecutions are summarized in Appendix N.
8.1.1 As informed by the Contractor, the major
construction activities for April 2018 are summarized in Table 8.1.
Table 8.1 Construction
Activities for April 2018
Site Area
|
Description
of Activities
|
Portion X
|
Dismantling/Trimming of Temporary
40mm Stone Platform for Construction of Seawall
|
Portion X
|
Construction of Seawall
|
Portion X
|
Loading and Unloading of
Filling Materials
|
Portion X
|
Backfilling at Scenic
Hill Tunnel (Cut & Cover Tunnel)
|
Airport Road
|
Works for Diversion of Airport
Road
|
Airport Road / Airport
Express Line / East Coast Road
|
Utilities Detection
|
Airport Road / Airport
Express Line/ East Coast Road
|
Establishment of Site
Access
|
Airport Road
|
E&M/
Backfilling/ Bitumen works for HKBCF to Airport Tunnel West (Cut & Cover
Tunnel)
|
Portion X
|
E&M/
Backfilling/ Bitumen works for HKBCF to Airport Tunnel East (Cut & Cover
Tunnel)
|
Portion X
|
Finishing works for
Highway Operation and Maintenance Area Building
|
West Portal
|
Finishing Works for
Scenic Hill Tunnel West Portal Ventilation building
|
8.2
Environmental
Monitoring Schedule for the Coming Month
8.2.1 The tentative schedule for
environmental monitoring in April 2018 is provided in Appendix D.
9.1.1
The construction phase and EM&A programme of the
Contract commenced on 17 October 2012. This is the sixty-sixth Monthly
EM&A report for the Contract which summarizes the monitoring results and
audit findings of the EM&A programme during the reporting period from 1 to 31
March 2018.
Air Quality
9.1.2 No Action and Limit Level
exceedances of 1-hr TSP were recorded at AMS5 and AMS6 during the reporting
month. No Action and Limit Level exceedances of 24-hr TSP were recorded at AMS5
and AMS6 during the reporting month.
Noise
9.1.3 For construction
noise, no Action and Limit Level exceedances were recorded at the monitoring
station during the reporting month.
Water Quality
9.1.4 For marine water quality monitoring, no Action Level and Limit Level
exceedances of dissolved oxygen level and turbidity level were recorded during
the reporting month. No Limit Level exceedances of suspended solids level were
recorded during the reporting month. Two Action Level exceedances of suspended
solids level were recorded during the reporting month. The exceedances of suspended
solid level are considered to be attributed to other external factors such as
sea condition, rather than the contract works. Therefore,
the exceedances were considered as non-contract related.
Dolphin
9.1.5 During the Marchˇ¦s
surveys of the Chinese White Dolphin, no adverse impact from the activities of this construction project on Chinese White Dolphins was
noticeable from general observations.
9.1.6
Due to monthly variation in dolphin occurrence within the study area, it
would be more appropriate to draw conclusion on whether any impacts on dolphins
have been detected related to the construction activities of this project in
the quarterly EM&A report, where comparison on distribution, group size and
encounter rates of dolphins between the quarterly impact monitoring period (March
ˇV May 2018) and baseline monitoring
period (3-month period) will be made.
Mudflat
9.1.7 This measurement result was
generally and relatively higher than the baseline measurement at S1, S2, S3 and
S4. The mudflat level is continuously increased.
9.1.8 The March 2018 survey results
indicate that the impacts of the HKLR project could not
be detected on horseshoe crabs and intertidal soft shore community. According
to the results of present survey, the disappearance of seagrass beds was
believed the cause of serial cyclone hits rather than impact of HKLR project.
Based on previous findings, the seagrass beds were expected to recolonize the
mudflat gradually in the future, as long as the vicinal water quality remained
normal. However, recolonization was yet to be recorded in present survey (Mar.
2018) after 3-6 months of disappearance. The results of
coming wet season survey (Jun. 2018) would provide a better understanding about
seagrass status
Environmental Site Inspection and Audit
9.1.9
Environmental site inspections were carried out on 1, 7, 14, 21 and 27 March
2018. Recommendations on remedial actions were given to the Contractors for the
deficiencies identified during the site inspections.
9.1.10 There was one complaint received
in relation to the environmental impacts (Cleanliness problem at East Coast
Road) which was mentioned in Monthly EM&A Report for December 2017. Complaint
investigation was undertaken. Based on the investigation
result, there is no direct evidence showing that that the complaint is related
to Contract No. HY/2011/03.
9.1.11 There was one complaint received in relation to the environmental impacts for
Monthly EM&A Report for February 2018. A follow-ups of complaint No. COM-2018-132 was received during reporting
period. Complaint Investigation is being undertaken.
9.1.12 No notification of summons and prosecution was
received during the reporting period.